CPWD Analysis of Rates · Roofing
Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete
Close fitting adjustable ridges
- Item number
- 12.12.3
- Analysis basis
- Details of cost for length of ridge 20.2 me-
- Priced inputs
- 6
- Derived rate
- ₹585.70 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.12.3 — Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete Close fitting adjustable ridges — is derived from 6 priced inputs for length of and works out to ₹585.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- tres Close fitting adjustable ridges
- Consider a shed of 20x10m (external dimensions at plinth).
- Length of ridges 20.2 metre
- No. of ridge pairs required, of length
- 1.22m each = 22.00 nos. +
- = 23.10 nos.x 1.22= 28.182 metre
- Add 5% wastage = 1.10 Nos.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0224 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement close fitting adjustable ridgeMaterial | metre | 28.182 | 230.00 | 6,481.86 |
| 9977 | CarriageMaterial | L.S. | 16.12 | 2.27 | 36.59 |
| 9999 | SundriesMaterial | L.S. | 7.15 | 2.27 | 16.23 |
| 0130 | MistryLabour | day | 0.14 | 897.00 | 125.58 |
| 0112 | Carpenter 2nd classLabour | day | 0.55 | 816.00 | 448.80 |
| 0114 | BeldarLabour | day | 1.64 | 736.00 | 1,207.04 |
- TOTAL
- 8,316.10
- Add 1 % Water charges on “W”
- 83.16
- TOTAL
- 8,399.26
- Add GST on “X” (multiplying factor 0.2127)
- 1,786.52
- TOTAL
- 10,185.78
- Add 15% CPOH on “Y”
- 1,527.87
- TOTAL
- 11,713.65
- Add Cess @ 1% on “Z”
- 117.14
- Cost of 20.20 metre
- 11,830.79
- Cost of 1.00 metre
- 585.68
- Say
- 585.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 866. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.