Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete

Close fitting adjustable ridges

Item number
12.12.3
Analysis basis
Details of cost for length of ridge 20.2 me-
Priced inputs
6
Derived rate
585.70 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.12.3 Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete Close fitting adjustable ridges — is derived from 6 priced inputs for length of and works out to ₹585.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • tres Close fitting adjustable ridges
  • Consider a shed of 20x10m (external dimensions at plinth).
  • Length of ridges 20.2 metre
  • No. of ridge pairs required, of length
  • 1.22m each = 22.00 nos. +
  • = 23.10 nos.x 1.22= 28.182 metre
  • Add 5% wastage = 1.10 Nos.
CodeInputUnitQuantityRate (INR)Amount (INR)
0224Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement close fitting adjustable ridgeMaterialmetre28.182230.006,481.86
9977CarriageMaterialL.S.16.122.2736.59
9999SundriesMaterialL.S.7.152.2716.23
0130MistryLabourday0.14897.00125.58
0112Carpenter 2nd classLabourday0.55816.00448.80
0114BeldarLabourday1.64736.001,207.04
TOTAL
8,316.10
Add 1 % Water charges on “W”
83.16
TOTAL
8,399.26
Add GST on “X” (multiplying factor 0.2127)
1,786.52
TOTAL
10,185.78
Add 15% CPOH on “Y”
1,527.87
TOTAL
11,713.65
Add Cess @ 1% on “Z”
117.14
Cost of 20.20 metre
11,830.79
Cost of 1.00 metre
585.68
Say
585.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 866. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.