Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete

Close fitting adjustable ridges
Item number
12.12.3
Analysis basis
length of
Priced inputs
6
Derived rate
₹585.70/ METRE
D-01/RATE ANALYSISITEM 12.12.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.12.3 (Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete Close fitting adjustable ridges) is derived from 6 priced inputs for length of and works out to ₹585.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • tres Close fitting adjustable ridges
  • Consider a shed of 20x10m (external dimensions at plinth).
  • Length of ridges 20.2 metre
  • No. of ridge pairs required, of length
  • 1.22m each = 22.00 nos. +
  • = 23.10 nos.x 1.22= 28.182 metre
  • Add 5% wastage = 1.10 Nos.
ANALYSIS OF RATES · ITEM 12.12.3DETAILS OF COST FOR LENGTH OF RIDGE 20.2 ME-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0224MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement close fitting adjustable ridgemetre28.182230.006,481.86
9977MATCarriageL.S.16.122.2736.59
9999MATSundriesL.S.7.152.2716.23
0130LABMistryday0.14897.00125.58
0112LABCarpenter 2nd classday0.55816.00448.80
0114LABBeldarday1.64736.001,207.04
BUILD-UP TO RATE
TOTAL
8,316.10
Add 1 % Water charges on “W”
+83.16
TOTAL
8,399.26
Add GST on “X” (multiplying factor 0.2127)
+1,786.52
TOTAL
10,185.78
Add 15% CPOH on “Y”
+1,527.87
TOTAL
11,713.65
Add Cess @ 1% on “Z”
+117.14
Cost of 20.20 metre
11,830.79
Cost of 1.00 metre
585.68
SAY
₹585.70
D-02/SOURCEPRINTED PAGE 866
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
866

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 866. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.