Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete

Plain wing adjustable ridges
Item number
12.12.2
Analysis basis
length of
Priced inputs
6
Derived rate
₹522.95/ METRE
D-01/RATE ANALYSISITEM 12.12.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.12.2 (Providing and fixing ridges and hips in fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing with suitable fixing accessories or self drilling fastener and EPDM washer etc. complete Plain wing adjustable ridges) is derived from 6 priced inputs for length of and works out to ₹522.95 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • tres Plain wing adjustable ridges
  • Consider a shed of 20x10m (external dimensions at plinth).
  • Length of ridges 20.2 metre
  • Ridge piece required each of 1.22m length =
  • 19 nos. +
  • 19.95 nos x 1.22 = 24.339 metre
  • Add 5% wastage = 0.95 No.
ANALYSIS OF RATES · ITEM 12.12.2DETAILS OF COST FOR LENGTH OF RIDGE 20.20 ME-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0226MATFibre reinforced by organic fibres and/or inorganic synthetic fibres cement plain wing adjustable ridgemetre24.339230.005,597.97
9977MATCarriage (The ridge is to be fixed with the same hooks as the Sheets)L.S.13.522.2730.69
9999MATSundriesL.S.6.762.2715.35
0130LABMistryday0.14897.00125.58
0112LABCarpenter 2nd classday0.55816.00448.80
0114LABBeldarday1.64736.001,207.04
BUILD-UP TO RATE
TOTAL
7,425.43
Add 1 % Water charges on “W”
+74.25
TOTAL
7,499.68
Add GST on “X” (multiplying factor 0.2127)
+1,595.18
TOTAL
9,094.86
Add 15% CPOH on “Y”
+1,364.23
TOTAL
10,459.09
Add Cess @ 1% on “Z”
+104.59
Cost of 20.20 metre
10,563.68
Cost of 1.00 metre
522.95
SAY
₹522.95
D-02/SOURCEPRINTED PAGE 865
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
865

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 865. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROOFING
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.