CPWD Analysis of Rates · Roofing
Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete
Eave’s filler pieces
- Item number
- 12.13.2
- Priced inputs
- 6
- Derived rate
- ₹345.05 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 12.13.2 — Providing and fixing fibre cement reinforced by organic fibres and/or inorganic synthetic fibres roofing accessories in all colours with polymer coated J or L hooks, bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and bitumen washers or with self drilling fastener and EPDM washer etc. complete: Eave’s filler pieces — is derived from 6 priced inputs and works out to ₹345.05 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Details of eaves filler for a shed of 20.2
- metres complete length
- Eaves filler pieces of 0.16 metres length =
- 20 nos.+
- Total = 21 nos.
- Add 5% wastage = 1.0 No.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0229 | Fibre reinforced by organic fibres and/or inorganic synthetic fibres cement eaves filler pieceMaterial | each | 21 | 190.00 | 3,990.00 |
| 9999 | The eaves filler pieces are to be fixed with the same hooks as the sheetsMaterial | L.S. | 3.25 | 2.27 | 7.38 |
| 9999 | SundriesMaterial | L.S. | 3.25 | 2.27 | 7.38 |
| 0130 | MistryLabour | day | 0.07 | 897.00 | 62.79 |
| 0112 | Carpenter 2nd classLabour | day | 0.28 | 816.00 | 228.48 |
| 0114 | BeldarLabour | day | 0.82 | 736.00 | 603.52 |
- TOTAL
- 4,899.55
- Add 1 % Water charges on “W”
- 49.00
- TOTAL
- 4,948.55
- Add GST on “X” (multiplying factor 0.2127)
- 1,052.56
- TOTAL
- 6,001.11
- Add 15% CPOH on “Y”
- 900.17
- TOTAL
- 6,901.28
- Add Cess @ 1% on “Z”
- 69.01
- Cost of 20.20 metres
- 6,970.29
- Cost of 1.00 metre
- 345.06
- Say
- 345.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 868. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.