Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12 (D=100 mm with tolerance of ± 2%) Zinc coated, Mesh wire diameter 3.0 mm, mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2mm, supplied @ 3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per direction of Engineer-in-charge

Item number
16.94
Priced inputs
5
Derived rate
₹4,178.00/ CUM
D-01/RATE ANALYSISITEM 16.94

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.94 (Providing & making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire mesh Gabion Boxes as per IS 16014:2012,MORTH Clause 2500, of required size, Mesh Type 10x12 (D=100 mm with tolerance of ± 2%) Zinc coated, Mesh wire diameter 3.0 mm, mechanically edged/selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2mm, supplied @ 3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per direction of Engineer-in-charge) is derived from 5 priced inputs and works out to ₹4,178.00 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details cost of one Gabion box/Crates of
  • size 2mx1mx1m = 2 cum
  • Surface area required = 11.00 sqm.
ANALYSIS OF RATES · ITEM 16.94
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8576MATCrates made of Mesh type 10x12 (D=100 mm) Zn coated. (Mesh wire diameter 3.00 mm)Powder coated Galvanized Iron intermediate cross-T section wire diameter 3.00 mm).sqm11230.002,530.00
7753MATStone boulder with least dimension 200mmStone Boulder 50 mm to 200 mmcum2875.001,750.00
0128LABMateday0.1816.0081.60
0125LABMason (for plain stone work) 2nd classday0.5816.00408.00
0114LABBeldarday1.5736.001,104.00
BUILD-UP TO RATE
TOTAL
5,873.60
Add 1 % Water charges on “W”
+58.74
TOTAL
5,932.34
Add GST on “X” (multiplying factor 0.2127)
+1,261.81
TOTAL
7,194.15
Add 15% CPOH on “Y”
+1,079.12
TOTAL
8,273.27
Add Cess @ 1% on “Z”
+82.73
Cost of 2 cum
8,356.00
Cost of 1 cum
4,178.00
SAY
₹4,178.00
D-02/SOURCEPRINTED PAGE 1276
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1276

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1276. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.