Providing and placing in position 100 mm thick factory made machine batched & machine mixed Precast RCC Rectangular Covers on drains of footpath of various sizes, of M-25 grade cement concrete for RCC work, including cost of centering, shuttering, reinforcement of 8 mm dia TMT bars of Fe 500 grade @ maximum 100mm c/c on both ways, neat cement punning on finished surface, properly encased on all edges with 1.6 mm thick, 100 mm wide MS sheet duly painted over priming coat, reinforcement to be welded at edges with MS sheet and providing 2 Nos. 12 mm dia bar for hooks etc including cost of cartage, all leads & lift, handling at site etc. all complete as per direction of Engineer-in-Charge

Item number
16.93
Analysis basis
Details of cost of 10 Nos. of size 1.50m
Priced inputs
6
Derived rate
3,081.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.93 Providing and placing in position 100 mm thick factory made machine batched & machine mixed Precast RCC Rectangular Covers on drains of footpath of various sizes, of M-25 grade cement concrete for RCC work, including cost of centering, shuttering, reinforcement of 8 mm dia TMT bars of Fe 500 grade @ maximum 100mm c/c on both ways, neat cement punning on finished surface, properly encased on all edges with 1.6 mm thick, 100 mm wide MS sheet duly painted over priming coat, reinforcement to be welded at edges with MS sheet and providing 2 Nos. 12 mm dia bar for hooks etc including cost of cartage, all leads & lift, handling at site etc. all complete as per direction of Engineer-in-Charge — is derived from 6 priced inputs and works out to ₹3,081.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • x0.40m = 6 sqm
  • Volume=6x0.10=0.60 cum
  • MATERIALS :
  • Precast RCC M-25
  • Reinforcement TMT
  • Welding by gas plant/ Electric plant
  • M.S. sheet 1.60 mm thick
  • 10x2x(1.50+0.40)x0.10x0.016x7850=47.7kg
  • Paint 10x2x(1.50+0.40)x0.10=3.8sqm
  • Neat Cement Punning
  • 10x1x1.50x0.40=6 sqm
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.5.33.1.1 of SH: REINFORCED CEMENT CONCRETERate as per item 5.33.1.1Sub-analysiscum0.69,504.755,702.85
Rate as per Item No.5.22.6 of SH: REINFORCED CEMENT CONCRETERate as per item 5.22.6Sub-analysisKg45.9107.854,950.32
Rate as per Item No.10.22 of SH: STEEL WORKRate as per item 10.22Sub-analysiscm8203.703,034.00
1013Mild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanksMaterialquintal0.4775,500.002,623.50
Rate as per Item No.13.61.1 of SH: FINISHINGRate as per item 13.61.1Sub-analysissqm3.8155.90592.42
Rate as per Item No.13.18 of SH: FINISHINGRate as per item 13.18Sub-analysissqm679.95479.70
TOTAL
17,382.79
Add 1 % Water charges on “W-A”
26.24
TOTAL
17,409.03
Add GST on “X-A” (multiplying factor 0.2127)
563.60
TOTAL
17,972.63
Add 15% CPOH on “Y-A”
482.00
TOTAL
18,454.63
Add Cess @ 1% on “Z-A”
36.95
Cost of 6 sqm.
18,491.58
Cost of 1 sqm.
3,081.93
Say
3,081.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1275. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.