Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity

Item number
16.9
Analysis basis
Details of cost for 100sqm.
Priced inputs
5
Derived rate
₹33.30
D-01/RATE ANALYSISITEM 16.9

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.9 (Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity) is derived from 5 priced inputs and works out to ₹33.30 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Consolidation of scarified material
  • 100sqm.x50mm = 5cum +
  • = 4 cum.
  • Less 20% wastage = 1 cum.
ANALYSIS OF RATES · ITEM 16.9DETAILS OF COST FOR 100SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday1.35736.00993.60
0115LABCoolieday1.08736.00794.88
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.1323,350.00442.20
0113LABChowkidarday0.132736.0097.15
9999MATSundriesL.S.5.462.2712.39
BUILD-UP TO RATE
TOTAL
2,340.22
Add 1 % Water charges on “W”
+23.40
TOTAL
2,363.62
Add GST on “X” (multiplying factor 0.2127)
+502.74
TOTAL
2,866.36
Add 15% CPOH on “Y”
+429.95
TOTAL
3,296.31
Add Cess @ 1% on “Z”
+32.96
Cost for 100 sqm.
3,329.27
Cost per sqm.
33.29
SAY
₹33.30
D-02/SOURCEPRINTED PAGE 1153
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1153

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1153. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.