Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity
- Item number
- 16.9
- Analysis basis
- Details of cost for 100sqm.
- Priced inputs
- 5
- Derived rate
- ₹33.30
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.9 (Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity) is derived from 5 priced inputs and works out to ₹33.30 after water charges, GST, CPOH and cess. The full build-up is below.
- Consolidation of scarified material
- 100sqm.x50mm = 5cum +
- = 4 cum.
- Less 20% wastage = 1 cum.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 1.35 | 736.00 | 993.60 |
| 0115 | LAB | Coolie | day | 1.08 | 736.00 | 794.88 |
| 0003 | MACH | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.132 | 3,350.00 | 442.20 |
| 0113 | LAB | Chowkidar | day | 0.132 | 736.00 | 97.15 |
| 9999 | MAT | Sundries | L.S. | 5.46 | 2.27 | 12.39 |
- TOTAL
- 2,340.22
- Add 1 % Water charges on “W”
- +23.40
- TOTAL
- 2,363.62
- Add GST on “X” (multiplying factor 0.2127)
- +502.74
- TOTAL
- 2,866.36
- Add 15% CPOH on “Y”
- +429.95
- TOTAL
- 3,296.31
- Add Cess @ 1% on “Z”
- +32.96
- Cost for 100 sqm.
- 3,329.27
- Cost per sqm.
- 33.29
- SAY
- ₹33.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1153
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1153. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.