CPWD Analysis of Rates · Road Work

Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity

Item number
16.9
Analysis basis
Details of cost for 100sqm.
Priced inputs
5
Derived rate
33.30

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.9 Scarifying metalled (water-bound) road surface including disposal of rubbish, lead upto 50 m and consolidation of the aggregate received from scarifying with power road roller of 8 to 10 tonne capacity — is derived from 5 priced inputs and works out to ₹33.30 after water charges, GST, CPOH and cess. The full build-up is below.

  • Consolidation of scarified material
  • 100sqm.x50mm = 5cum +
  • = 4 cum.
  • Less 20% wastage = 1 cum.
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday1.35736.00993.60
0115CoolieLabourday1.08736.00794.88
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.1323,350.00442.20
0113ChowkidarLabourday0.132736.0097.15
9999SundriesMaterialL.S.5.462.2712.39
TOTAL
2,340.22
Add 1 % Water charges on “W”
23.40
TOTAL
2,363.62
Add GST on “X” (multiplying factor 0.2127)
502.74
TOTAL
2,866.36
Add 15% CPOH on “Y”
429.95
TOTAL
3,296.31
Add Cess @ 1% on “Z”
32.96
Cost for 100 sqm.
3,329.27
Cost per sqm.
33.29
Say
33.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1153. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works