Brick edging laid lengthwise with half brick depth including excavation, refilling and disposal of surplus earth lead upto 50 metres

With common burnt clay F.P.S. (non modular) bricks of class designation 7.5

Item number
16.8.1
Analysis basis
Details of cost for 10 metre
Priced inputs
5
Derived rate
53.45 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.8.1 Brick edging laid lengthwise with half brick depth including excavation, refilling and disposal of surplus earth lead upto 50 metres: With common burnt clay F.P.S. (non modular) bricks of class designation 7.5 — is derived from 5 priced inputs for 10 metre and works out to ₹53.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • including 12% wastage
CodeInputUnitQuantityRate (INR)Amount (INR)
2602Common burnt clay F.P.S. (non modular) bricks class designation 7.5Material1000 Nos0.0494,724.00231.48
0123Mason 1st classMason 1st classLabourday0.04897.0035.88
0124Mason 2nd classMason 2nd classLabourday0.04816.0032.64
0115CoolieLabourday0.09736.0066.24
9999Removal of rubbishMaterialL.S.4.162.279.44
TOTAL
375.68
Add 1 % Water charges on “W”
3.76
TOTAL
379.44
Add GST on “X” (multiplying factor 0.2127)
80.71
TOTAL
460.15
Add 15% CPOH on “Y”
69.02
TOTAL
529.17
Add Cess @ 1% on “Z”
5.29
Cost for 10 metre
534.46
Cost per metre
53.45
Say
53.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1152. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.