CPWD Analysis of Rates · Road Work
Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost)
- Item number
- 16.85
- Analysis basis
- Details of cost for 100 metre
- Priced inputs
- 5
- Derived rate
- ₹109.45 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.85 — Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost) — is derived from 5 priced inputs for 100 metre and works out to ₹109.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Number of kerb stones = 100 / 0.405= 247
- Nos.
- Qty. = 247 x 0.40 x 0.375 x 0.20 = 7.41cum
- No. of joints = 247 - 1 = 246 Nos.
- Cement Mortar 1:3 for fixing joints = 246
- x[(0.115 + 0.20)/2 x 0.375 x 0.005] = 0.073
- cum
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per Item No.3.8 of SH:MORTARSRate as per item 3.8Sub-analysis | cum | 0.073 | 4,881.95 | 356.38 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 2.5 | 816.00 | 2,040.00 |
| 0114 | BeldarLabour | day | 2.5 | 736.00 | 1,840.00 |
| 0115 | CoolieLabour | day | 1.65 | 736.00 | 1,214.40 |
- TOTAL
- 7,693.28
- Add 1 % Water charges on “W”
- 76.93
- TOTAL
- 7,770.21
- Add GST on “X” (multiplying factor 0.2127)
- 1,652.72
- TOTAL
- 9,422.93
- Add 15% CPOH on “Y”
- 1,413.44
- TOTAL
- 10,836.37
- Add Cess @ 1% on “Z”
- 108.36
- Cost of 100 metre
- 10,944.73
- Cost of 1 metre
- 109.45
- Say
- 109.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1269. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.