Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost)

Item number
16.85
Analysis basis
100 metre
Priced inputs
5
Derived rate
₹109.45/ METRE
D-01/RATE ANALYSISITEM 16.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.85 (Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost)) is derived from 5 priced inputs for 100 metre and works out to ₹109.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Number of kerb stones = 100 / 0.405= 247
  • Nos.
  • Qty. = 247 x 0.40 x 0.375 x 0.20 = 7.41cum
  • No. of joints = 247 - 1 = 246 Nos.
  • Cement Mortar 1:3 for fixing joints = 246
  • x[(0.115 + 0.20)/2 x 0.375 x 0.005] = 0.073
  • cum
ANALYSIS OF RATES · ITEM 16.85DETAILS OF COST FOR 100 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.3.8 of SH:MORTARSRate as per item 3.8cum0.0734,881.95356.38
0123LABMason 1st classMason 1st classday2.5897.002,242.50
0124LABMason 2nd classMason 2nd classday2.5816.002,040.00
0114LABBeldarday2.5736.001,840.00
0115LABCoolieday1.65736.001,214.40
BUILD-UP TO RATE
TOTAL
7,693.28
Add 1 % Water charges on “W”
+76.93
TOTAL
7,770.21
Add GST on “X” (multiplying factor 0.2127)
+1,652.72
TOTAL
9,422.93
Add 15% CPOH on “Y”
+1,413.44
TOTAL
10,836.37
Add Cess @ 1% on “Z”
+108.36
Cost of 100 metre
10,944.73
Cost of 1 metre
109.45
SAY
₹109.45
D-02/SOURCEPRINTED PAGE 1269
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1269

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1269. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK