Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost)

Item number
16.85
Analysis basis
Details of cost for 100 metre
Priced inputs
5
Derived rate
109.45 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.85 Laying at or near ground level old kerb stones of all types in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement : 3 coarse sand), including making joints with or without grooves (thickness of joints, except at sharp curve, shall not be more than 5 mm), including making drainage opening wherever required etc. complete as per direction of Engineer-in-charge. (Length of finished kerb edging shall be measured for payment). (Old kerb stones shall be supplied by the department free of cost) — is derived from 5 priced inputs for 100 metre and works out to ₹109.45 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Number of kerb stones = 100 / 0.405= 247
  • Nos.
  • Qty. = 247 x 0.40 x 0.375 x 0.20 = 7.41cum
  • No. of joints = 247 - 1 = 246 Nos.
  • Cement Mortar 1:3 for fixing joints = 246
  • x[(0.115 + 0.20)/2 x 0.375 x 0.005] = 0.073
  • cum
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.3.8 of SH:MORTARSRate as per item 3.8Sub-analysiscum0.0734,881.95356.38
0123Mason 1st classMason 1st classLabourday2.5897.002,242.50
0124Mason 2nd classMason 2nd classLabourday2.5816.002,040.00
0114BeldarLabourday2.5736.001,840.00
0115CoolieLabourday1.65736.001,214.40
TOTAL
7,693.28
Add 1 % Water charges on “W”
76.93
TOTAL
7,770.21
Add GST on “X” (multiplying factor 0.2127)
1,652.72
TOTAL
9,422.93
Add 15% CPOH on “Y”
1,413.44
TOTAL
10,836.37
Add Cess @ 1% on “Z”
108.36
Cost of 100 metre
10,944.73
Cost of 1 metre
109.45
Say
109.45

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1269. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works