CPWD Analysis of Rates · Road Work

Laying old cement cocrete interlocking paver blocks of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-incharge. (Old CC paver blocks shall be supplied by the department free of cost)

Item number
16.84
Analysis basis
Details of cost for 10 sqm.
Priced inputs
6
Derived rate
402.95 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.84 Laying old cement cocrete interlocking paver blocks of any design/ shape laid in required line, level, curvature, colour and pattern over and including 50 mm thick compacted bed of coarse sand, filling the joints with fine sand etc. all complete as per the direction of Engineer-incharge. (Old CC paver blocks shall be supplied by the department free of cost) — is derived from 6 priced inputs for 10 sqm and works out to ₹402.95 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Bedding layer 50mm thick
  • Qty = 10 x 0.05 = 0.50 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
0982Coarse sand (zone III)Materialcum0.51,450.00725.00
0983Fine sand (zone IV)Materialcum0.15980.00147.00
0123Mason 1st classMason 1st classLabourday0.5897.00448.50
0124Mason 2nd classMason 2nd classLabourday0.5816.00408.00
0114BeldarLabourday1736.00736.00
0115CoolieLabourday0.5736.00368.00
TOTAL
2,832.50
Add 1 % Water charges on “W”
28.33
TOTAL
2,860.83
Add GST on “X” (multiplying factor 0.2127)
608.50
TOTAL
3,469.33
Add 15% CPOH on “Y”
520.40
TOTAL
3,989.73
Add Cess @ 1% on “Z”
39.90
Cost of 10 sqm.
4,029.63
Cost of 1 sqm
402.96
Say
402.95

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1268. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.