CPWD Analysis of Rates · Road Work
Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge
- Item number
- 16.83
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 3
- Derived rate
- ₹131.75 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.83 — Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge — is derived from 3 priced inputs for 10 sqm and works out to ₹131.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.25 | 736.00 | 184.00 |
| 0115 | CoolieLabour | day | 1 | 736.00 | 736.00 |
| 9999 | SundriesMaterial | L.S. | 2.7 | 2.27 | 6.13 |
- TOTAL
- 926.13
- Add 1 % Water charges on “W”
- 9.26
- TOTAL
- 935.39
- Add GST on “X” (multiplying factor 0.2127)
- 198.96
- TOTAL
- 1,134.35
- Add 15% CPOH on “Y”
- 170.15
- TOTAL
- 1,304.50
- Add Cess @ 1% on “Z”
- 13.05
- Cost of 10 sqm.
- 1,317.55
- Cost of 1 sqm
- 131.76
- Say
- 131.75
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1268. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works