Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge

Item number
16.83
Analysis basis
10 sqm
Priced inputs
3
Derived rate
₹131.75/ SQM
D-01/RATE ANALYSISITEM 16.83

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.83 (Taking out existing CC interlocking paver blocks from footpath/ central verge, including removal of rubbish etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge) is derived from 3 priced inputs for 10 sqm and works out to ₹131.75 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 16.83DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.25736.00184.00
0115LABCoolieday1736.00736.00
9999MATSundriesL.S.2.72.276.13
BUILD-UP TO RATE
TOTAL
926.13
Add 1 % Water charges on “W”
+9.26
TOTAL
935.39
Add GST on “X” (multiplying factor 0.2127)
+198.96
TOTAL
1,134.35
Add 15% CPOH on “Y”
+170.15
TOTAL
1,304.50
Add Cess @ 1% on “Z”
+13.05
Cost of 10 sqm.
1,317.55
Cost of 1 sqm
131.76
SAY
₹131.75
D-02/SOURCEPRINTED PAGE 1268
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1268

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1268. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK