Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge

Item number
16.82
Analysis basis
100 metre
Priced inputs
3
Derived rate
₹39.35/ METRE
D-01/RATE ANALYSISITEM 16.82

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.82 (Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge) is derived from 3 priced inputs for 100 metre and works out to ₹39.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 16.82DETAILS OF COST FOR 100 METRE
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.75736.00552.00
0115LABCoolieday3736.002,208.00
9999MATSundriesL.S.22.274.54
BUILD-UP TO RATE
TOTAL
2,764.54
Add 1 % Water charges on “W”
+27.65
TOTAL
2,792.19
Add GST on “X” (multiplying factor 0.2127)
+593.90
TOTAL
3,386.09
Add 15% CPOH on “Y”
+507.91
TOTAL
3,894.00
Add Cess @ 1% on “Z”
+38.94
Cost of 100 metre
3,932.94
Cost of 1 metre
39.33
SAY
₹39.35
D-02/SOURCEPRINTED PAGE 1267
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1267

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1267. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.