Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge
- Item number
- 16.82
- Analysis basis
- 100 metre
- Priced inputs
- 3
- Derived rate
- ₹39.35/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.82 (Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge) is derived from 3 priced inputs for 100 metre and works out to ₹39.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 0.75 | 736.00 | 552.00 |
| 0115 | LAB | Coolie | day | 3 | 736.00 | 2,208.00 |
| 9999 | MAT | Sundries | L.S. | 2 | 2.27 | 4.54 |
- TOTAL
- 2,764.54
- Add 1 % Water charges on “W”
- +27.65
- TOTAL
- 2,792.19
- Add GST on “X” (multiplying factor 0.2127)
- +593.90
- TOTAL
- 3,386.09
- Add 15% CPOH on “Y”
- +507.91
- TOTAL
- 3,894.00
- Add Cess @ 1% on “Z”
- +38.94
- Cost of 100 metre
- 3,932.94
- Cost of 1 metre
- 39.33
- SAY
- ₹39.35
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1267
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1267. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.