Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge

Item number
16.82
Analysis basis
Details of cost for 100 metre
Priced inputs
3
Derived rate
39.35 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.82 Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge — is derived from 3 priced inputs for 100 metre and works out to ₹39.35 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.75736.00552.00
0115CoolieLabourday3736.002,208.00
9999SundriesMaterialL.S.22.274.54
TOTAL
2,764.54
Add 1 % Water charges on “W”
27.65
TOTAL
2,792.19
Add GST on “X” (multiplying factor 0.2127)
593.90
TOTAL
3,386.09
Add 15% CPOH on “Y”
507.91
TOTAL
3,894.00
Add Cess @ 1% on “Z”
38.94
Cost of 100 metre
3,932.94
Cost of 1 metre
39.33
Say
39.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1267. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works