Providing and laying gang saw cut 18 mm thick, mirror polished pre moulded and pre polished machine cut granite stone of required size and shape of approved shade, colour and texture in footpath, flooring cut granite stone of required size and shape of approved shade, colour and texture in footpath, flooring in road side plazas and similar locations, laid over 20mm thick base of cement mortar 1:4 (1cement : 4 coarse sand) including grouting the joints with white cement mixed with matching pigment, epoxy touch ups etc. complete as per direction of Engineer-in-Charge

With granite stone of area less than 0.50 sqm
Item number
16.86.1
Analysis basis
Detail of cost for 0.5sqm.
Priced inputs
6
Derived rate
₹4,746.20
D-01/RATE ANALYSISITEM 16.86.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.86.1 (Providing and laying gang saw cut 18 mm thick, mirror polished pre moulded and pre polished machine cut granite stone of required size and shape of approved shade, colour and texture in footpath, flooring cut granite stone of required size and shape of approved shade, colour and texture in footpath, flooring in road side plazas and similar locations, laid over 20mm thick base of cement mortar 1:4 (1cement : 4 coarse sand) including grouting the joints with white cement mixed with matching pigment, epoxy touch ups etc. complete as per direction of Engineer-in-Charge With granite stone of area less than 0.50 sqm) is derived from 6 priced inputs and works out to ₹4,746.20 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Mirror polished granite 0.5 sqm.
  • Waste @5% = 0.025 +0.5 = 0.525 sqm.
  • LABOUR :
ANALYSIS OF RATES · ITEM 16.86.1DETAIL OF COST FOR 0.5SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7295MATGranite of any colour, 18 mm thick (slab area upto 0.50 sqm)Granite of colour black, cherry/ruby red 18 mm thick (slab area upto 0.50 sqm)sqm0.5251,908.001,001.70
SUBRate as per Item No.3.9 of SH: MORTARSRate as per item 3.9cum0.0124,211.7050.54
0123LABMason 1st classMason 1st classday0.56897.00502.32
0114LABBeldarday0.05736.0036.80
0115LABCoolieday0.05736.0036.80
9999MATSundriesL.S.17.62.2739.95
BUILD-UP TO RATE
TOTAL
1,668.11
Add 1 % Water charges on “W”
+16.68
TOTAL
1,684.79
Add GST on “X” (multiplying factor 0.2127)
+358.35
TOTAL
2,043.14
Add 15% CPOH on “Y”
+306.47
TOTAL
2,349.61
Add Cess @ 1% on “Z”
+23.50
Cost of 0.5 sqm
2,373.11
Cost per sqm.
4,746.22
SAY
₹4,746.20
D-02/SOURCEPRINTED PAGE 1269
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1269

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1269. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.