CPWD Analysis of Rates · Road Work

Sub analysis item for material component of Item No. 16.81

Item number
16.81X
Analysis basis
Details of cost for 2.5 metre
Priced inputs
4
Derived rate
53.70 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.81X Sub analysis item for material component of Item No. 16.81 — is derived from 4 priced inputs for 2.5 metre and works out to ₹53.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.

  • Sub analysis item no.16.81X to be used in
  • Item No. 16.81
  • M.S. Sheet 1.63mm thick = 1x2.50x2.00
  • = 5.00 sqm @ 12.80 kg/sqm = 64.00 kg
  • wastage @ 5%= 3.20 kg
  • Total = 67.20 kg
  • MS Angle - 40 x 40 x 6 mm
  • Outframe=2x(2.50+2.00)=9.00 m
  • Vertical extra = 2x0.300 = 0.60 m
  • Horizontal = 1x2.50 =2.50 m
  • Bracing = 2x3.20 = 6.40 m
  • Bracing at bottom = 2x0.50 = 1.00 m
  • Total = 19.50 m @ 3.50 kg/m = 68.25 kg +
  • wastage @ 5% = 3.14 kg
  • Total = 71.66 kg
  • M.S. Channel = 2x0.50 =1.00 m @
  • 5.70 kg/m = 5.70 kg+
  • wastage @ 5% = 0.29 kg
  • Total = 5.99 kg
  • M.S. Flat 30x5 mm
  • Horizontal = 2x2.50 = 5.00 m
  • Vertical = 2x2.00 = 4.00 m
  • Total = 9.00 m @ 1.20 kg/m = 10.80 kg +
  • wastage @ 5% = 0.54 kg
  • Total = 11.34 kg
  • Assuming that material will become
  • unserviceable after using 40 times, cost of
  • 2.5 metre using once = S/40
CodeInputUnitQuantityRate (INR)Amount (INR)
1013Mild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanksMaterialquintal0.6725,500.003,696.00
1007Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal0.7175,965.004,276.91
1007Structurals such as tees, angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterialquintal0.065,965.00357.90
1008Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterialquintal0.1135,450.00615.85
TOTAL
8,946.66
Add for maintenance @ 10% on P
894.67
Less for salvage value of material @ 50% on P
-4,473.53
TOTAL
5,368.00
Cost of 2.5 metre
134.20
Cost of 1 metre
53.68
Say
53.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1266. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.