CPWD Analysis of Rates · Road Work
Sub analysis item for material component of Item No. 16.81
- Item number
- 16.81X
- Analysis basis
- Details of cost for 2.5 metre
- Priced inputs
- 4
- Derived rate
- ₹53.70 / metre
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.81X — Sub analysis item for material component of Item No. 16.81 — is derived from 4 priced inputs for 2.5 metre and works out to ₹53.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Sub analysis item no.16.81X to be used in
- Item No. 16.81
- M.S. Sheet 1.63mm thick = 1x2.50x2.00
- = 5.00 sqm @ 12.80 kg/sqm = 64.00 kg
- wastage @ 5%= 3.20 kg
- Total = 67.20 kg
- MS Angle - 40 x 40 x 6 mm
- Outframe=2x(2.50+2.00)=9.00 m
- Vertical extra = 2x0.300 = 0.60 m
- Horizontal = 1x2.50 =2.50 m
- Bracing = 2x3.20 = 6.40 m
- Bracing at bottom = 2x0.50 = 1.00 m
- Total = 19.50 m @ 3.50 kg/m = 68.25 kg +
- wastage @ 5% = 3.14 kg
- Total = 71.66 kg
- M.S. Channel = 2x0.50 =1.00 m @
- 5.70 kg/m = 5.70 kg+
- wastage @ 5% = 0.29 kg
- Total = 5.99 kg
- M.S. Flat 30x5 mm
- Horizontal = 2x2.50 = 5.00 m
- Vertical = 2x2.00 = 4.00 m
- Total = 9.00 m @ 1.20 kg/m = 10.80 kg +
- wastage @ 5% = 0.54 kg
- Total = 11.34 kg
- Assuming that material will become
- unserviceable after using 40 times, cost of
- 2.5 metre using once = S/40
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 1013 | Mild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanksMaterial | quintal | 0.672 | 5,500.00 | 3,696.00 |
| 1007 | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterial | quintal | 0.717 | 5,965.00 | 4,276.91 |
| 1007 | Structurals such as tees, angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joistsMaterial | quintal | 0.06 | 5,965.00 | 357.90 |
| 1008 | Flats upto 10 mm in thicknessFlats up to 10 mm in thicknessMaterial | quintal | 0.113 | 5,450.00 | 615.85 |
- TOTAL
- 8,946.66
- Add for maintenance @ 10% on P
- 894.67
- Less for salvage value of material @ 50% on P
- -4,473.53
- TOTAL
- 5,368.00
- Cost of 2.5 metre
- 134.20
- Cost of 1 metre
- 53.68
- Say
- 53.70
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1266. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works