Sub analysis item for material component of Item No. 16.81
- Item number
- 16.81X
- Analysis basis
- 2.5 metre
- Priced inputs
- 4
- Derived rate
- ₹53.70/ METRE
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.81X (Sub analysis item for material component of Item No. 16.81) is derived from 4 priced inputs for 2.5 metre and works out to ₹53.70 per metre after water charges, GST, CPOH and cess. The full build-up is below.
- Sub analysis item no.16.81X to be used in
- Item No. 16.81
- M.S. Sheet 1.63mm thick = 1x2.50x2.00
- = 5.00 sqm @ 12.80 kg/sqm = 64.00 kg
- wastage @ 5%= 3.20 kg
- Total = 67.20 kg
- MS Angle - 40 x 40 x 6 mm
- Outframe=2x(2.50+2.00)=9.00 m
- Vertical extra = 2x0.300 = 0.60 m
- Horizontal = 1x2.50 =2.50 m
- Bracing = 2x3.20 = 6.40 m
- Bracing at bottom = 2x0.50 = 1.00 m
- Total = 19.50 m @ 3.50 kg/m = 68.25 kg +
- wastage @ 5% = 3.14 kg
- Total = 71.66 kg
- M.S. Channel = 2x0.50 =1.00 m @
- 5.70 kg/m = 5.70 kg+
- wastage @ 5% = 0.29 kg
- Total = 5.99 kg
- M.S. Flat 30x5 mm
- Horizontal = 2x2.50 = 5.00 m
- Vertical = 2x2.00 = 4.00 m
- Total = 9.00 m @ 1.20 kg/m = 10.80 kg +
- wastage @ 5% = 0.54 kg
- Total = 11.34 kg
- Assuming that material will become
- unserviceable after using 40 times, cost of
- 2.5 metre using once = S/40
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 1013 | MAT | Mild steel sheets for tanksMild steel sheets of 1.00 mm thickness for tanks | quintal | 0.672 | 5,500.00 | 3,696.00 |
| 1007 | MAT | Structurals such as tees,angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joists | quintal | 0.717 | 5,965.00 | 4,276.91 |
| 1007 | MAT | Structurals such as tees, angles channels and R.S. joistsStructural steel such as tees, angles channels and R.S. joists | quintal | 0.06 | 5,965.00 | 357.90 |
| 1008 | MAT | Flats upto 10 mm in thicknessFlats up to 10 mm in thickness | quintal | 0.113 | 5,450.00 | 615.85 |
- TOTAL
- 8,946.66
- Add for maintenance @ 10% on P
- +894.67
- Less for salvage value of material @ 50% on P
- -4,473.53
- TOTAL
- 5,368.00
- Cost of 2.5 metre
- 134.20
- Cost of 1 metre
- 53.68
- SAY
- ₹53.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1266
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1266. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.