Providing and erecting 2.00 metre high temporary barricading at site; each panel of size 2.50 m x2.00 m made of 40x40x6 mm angle iron or 50x50x3 mm hollow MS tube posts/horizontal members/bracings covered with 1.63 mm thick MS sheet. The sheet shall be fixed with 30x5 mm MS flat by suitable welding/riveting. The panels shall be made so that gap of 50cm above the ground is available making overall height as 2.5 m. MS channel ISLC 75 @ 5.70 kg/m, 50 cm long shall be provided at the bottom having oval shaped holes of size 50x25 mm at both ends with 50 cm long MS angle 40x40x6 mm bracing. Suitable arrangement shall be made to fix the barricading to avoid from overturning by providing 250 mm long expansion fasteners at both ends. The work shall be executed as per drawing/direction of Engineer-in-Charge which includes writing and painting, arrangement for traffic diversion such as traffic signals during construction at site for day and night, glow lamps, reflective signs, marking, flags, caution tape as directed by the Engineer-in-Charge. The barricading provided shall be retained in position at site continuously including shifting of barricading from one location to another location as many times as required during the execution of the entire work till its completion. Rate include its maintenance for damages, painting, all incidentals, labour materials, equipments and works required to execute the job. The barricading shall not be removed without prior approval of Engineer-in-Charge. (Note :- One time payment shall be made for providing barricading from start of work till completion of work including shifting. The barricading provided shall remain to be the property of the contractor on completion of the work)

Item number
16.81
Analysis basis
Details of cost for 2.5 metre
Priced inputs
4
Derived rate
3,439.50 / metre

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.81 Providing and erecting 2.00 metre high temporary barricading at site; each panel of size 2.50 m x2.00 m made of 40x40x6 mm angle iron or 50x50x3 mm hollow MS tube posts/horizontal members/bracings covered with 1.63 mm thick MS sheet. The sheet shall be fixed with 30x5 mm MS flat by suitable welding/riveting. The panels shall be made so that gap of 50cm above the ground is available making overall height as 2.5 m. MS channel ISLC 75 @ 5.70 kg/m, 50 cm long shall be provided at the bottom having oval shaped holes of size 50x25 mm at both ends with 50 cm long MS angle 40x40x6 mm bracing. Suitable arrangement shall be made to fix the barricading to avoid from overturning by providing 250 mm long expansion fasteners at both ends. The work shall be executed as per drawing/direction of Engineer-in-Charge which includes writing and painting, arrangement for traffic diversion such as traffic signals during construction at site for day and night, glow lamps, reflective signs, marking, flags, caution tape as directed by the Engineer-in-Charge. The barricading provided shall be retained in position at site continuously including shifting of barricading from one location to another location as many times as required during the execution of the entire work till its completion. Rate include its maintenance for damages, painting, all incidentals, labour materials, equipments and works required to execute the job. The barricading shall not be removed without prior approval of Engineer-in-Charge. (Note :- One time payment shall be made for providing barricading from start of work till completion of work including shifting. The barricading provided shall remain to be the property of the contractor on completion of the work) — is derived from 4 priced inputs for 2.5 metre and works out to ₹3,439.50 per metre after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Sub Analysis No.16.81XRate as per item 16.81XSub-analysismetre2.553.70134.25
Rate as per Sub Analysis No.16.81YRate as per item 16.81YSub-analysismetre2.51,673.354,183.38
Rate as per Item No.13.50.3 of SH: FINISHINGRate as per item 13.50.3Sub-analysissqm1167.40741.40
Rate as per Item No.13.61.1 of SH: FINISHINGRate as per item 13.61.1Sub-analysissqm11155.901,714.90
TOTAL
6,773.93
Add 1 % Water charges on “W-A”
43.18
TOTAL
6,817.11
Add GST on “X-A” (multiplying factor 0.2127)
927.54
TOTAL
7,744.65
Add 15% CPOH on “Y-A”
793.25
TOTAL
8,537.90
Add Cess @ 1% on “Z-A”
60.82
Cost of 2.5 metre
8,598.72
Cost of 1 metre
3,439.49
Say
3,439.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1265. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.