Skip to main content
R/DAR 2023

Construction of dry lean cement concrete sub base over a prepared sub-grade with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per specifications, cement content not to be less than 150 Kg/cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, for all leads & lifts, laid with a mechanical paver, compacting with 8-10 tonne vibratory roller, finishing and curing etc. complete as per direction of Engineer-incharge

Item number
16.80
Analysis basis
450 cum
Priced inputs
14
Derived rate
₹4,148.65/ CUM
D-01/RATE ANALYSISITEM 16.80

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.80 (Construction of dry lean cement concrete sub base over a prepared sub-grade with coarse and fine aggregate conforming to IS:383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per specifications, cement content not to be less than 150 Kg/cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, for all leads & lifts, laid with a mechanical paver, compacting with 8-10 tonne vibratory roller, finishing and curing etc. complete as per direction of Engineer-incharge) is derived from 14 priced inputs for 450 cum and works out to ₹4,148.65 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Crushed stone coarse aggregate of
  • 25mm & 12.5 mm nominal sizes graded
  • as per specifications @ 0.90 cum/cum of
  • concrete conforming to specification. = 405
  • cum Coarse Sand @0.45 m3 per cum of
  • concrete = 203 cum
  • Cement @150 Kg. per cum of concrete=
  • 67.50 cum
  • Qty for 0294,0296 codes = 405 / 2 = 202.50
  • cum
  • @75 tonne capacity
  • 5 km lead with one trip per hour
  • Tipper 10 tonne capacity (Taken 10km
  • average lead)
  • 990x10=9900 tonne km
ANALYSIS OF RATES · ITEM 16.80DETAILS OF COST FOR 450 CUM (990 TONNE)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0294MATStone Aggregate (Single size) : 25 mm nominal sizecum202.51,400.002,83,500.00
0296MATStone Aggregate (Single size) : 12.5 mm nominal sizecum202.51,400.002,83,500.00
0982MATCoarse sand (zone III)cum2031,450.002,94,350.00
0367MATPortland Cement (OPC-43 grade)tonne67.55,156.003,48,030.00
0052MACHFront end loader 1 cum bucket capacity (incl POL)hour61,450.008,700.00
0066MACHBatching and Mixing Plant @ 75 cum per hourhour62,700.0016,200.00
0069MACHGenerator 250 KVAhour6450.002,700.00
0065MACHPaver finisher Mechanical 100 TPHhour6900.005,400.00
0054MACHVibratory roller 8 to 10 tonnehour8700.005,600.00
0057MACHWater Tanker 5 to 6 KL capacityhour8250.002,000.00
0053MACHTipper -5 CumTipper-5 Cum/10 tonnestonne km9,9003.7036,630.00
0128LABMateday1.12816.00913.92
0139LABSkilled Beldar (for floor rubbing etc.)day6816.004,896.00
0114LABBeldarday22736.0016,192.00
BUILD-UP TO RATE
Add 10 per cent of cost of carriage to cover cost of loading and unloading
+3,663.00
TOTAL
13,12,274.92
Add 1 % Water charges on “W”
+13,122.75
TOTAL
13,25,397.67
Add GST on “X” (multiplying factor 0.2127)
+2,81,912.08
TOTAL
16,07,309.75
Add 15% CPOH on “Y”
+2,41,096.46
TOTAL
18,48,406.21
Add Cess @ 1% on “Z”
+18,484.06
Cost for 450 cum(990 Tonne)
18,66,890.27
Cost per cum.
4,148.65
SAY
₹4,148.65
D-02/SOURCEPRINTED PAGE 1264
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1264

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1264. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.