Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm ) to wet mix macadam (WMM) specification including premixing the material with water at OMC in for all leads & lifts, laying in uniform layers with mechanical paver finisher in subbase / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achievethe desired density, complete as per specifications and directions of Engineer-in-Charge

Item number
16.79
Analysis basis
225 cum
Priced inputs
19
Derived rate
₹2,914.30/ CUM
D-01/RATE ANALYSISITEM 16.79

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.79 (Providing, laying, spreading and compacting graded stone aggregate (size range 53 mm to 0.075 mm ) to wet mix macadam (WMM) specification including premixing the material with water at OMC in for all leads & lifts, laying in uniform layers with mechanical paver finisher in subbase / base course on well prepared surface and compacting with vibratory roller of 8 to 10 tonne capacity to achievethe desired density, complete as per specifications and directions of Engineer-in-Charge) is derived from 19 priced inputs for 225 cum and works out to ₹2,914.30 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Conforming to table ……
  • 45mm to22.4mm @ 30% = 89.10 cum
  • Qty for 0292,0293,0294,0295 codes =
  • 89.10 / 4 = 22.275 cum
  • Qty for 2206, 2202 codes = 89.10 /2 = 44.55
  • cum
  • 22.4 mm to 2.36mm @ 40% = 118.80 cum
  • Qty for 0294,0295 codes = 118.80 /4 =
  • 29.70 cum
  • Qty for 1179 code = 118.80 /2 = 59.40 cum
  • 2.36 mm to 75 microon @ 30% = 89.10 cum
  • Qty for 2903, 2904 codes = 89.10 / 2 =
  • 44.55 cum
  • @75 tonne capacity
  • 5 km lead with one trip per hour
  • Tipper 10 tonne capacity( taking lead= 10
  • Km) =495x10 =4950 tonne km
ANALYSIS OF RATES · ITEM 16.79DETAILS OF COST FOR 225 CUM (495 TONNE)
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0292MATStone Aggregate (Single size) : 50 mm nominal sizecum22.2751,100.0024,502.50
0293MATStone Aggregate (Single size) : 40 mm nominal sizecum22.2751,400.0031,185.00
0294MATStone Aggregate (Single size) : 25 mm nominal sizecum22.2751,400.0031,185.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum22.2751,425.0031,741.88
0294MATStone Aggregate (Single size) : 25 mm nominal sizecum29.71,400.0041,580.00
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum29.71,425.0042,322.50
1179MATCrushed stone 2.36 mm to 12.5 mm sizecum59.41,005.0059,697.00
2903MATStone chippings/ screenings 4.75 mm nominal sizecum44.551,600.0071,280.00
2904MATStone chippings/ screenings 150 micron nominal sizecum44.551,600.0071,280.00
0059MACHWet Mix Plant 60 TPHhour6.61,050.006,930.00
0070MACHGenerator 100 KVA/125 KVAhour6350.002,100.00
0057MACHWater Tanker 5 to 6 KL capacityhour3250.00750.00
0052MACHFront end loader 1 cum bucket capacity (incl POL)hour61,450.008,700.00
0053MACHTipper -5 CumTipper-5 Cum/10 tonnestonne km4,9503.7018,315.00
0065MACHPaver finisher Mechanical 100 TPHhour6900.005,400.00
0054MACHVibratory roller 8 to 10 tonnehour3.9700.002,730.00
0128LABMateday0.48816.00391.68
0139LABSkilled Beldar (for floor rubbing etc.)day2816.001,632.00
0114LABBeldarday10736.007,360.00
BUILD-UP TO RATE
Add 10 per cent of cost of carriage to cover cost of loading and unloading
+1,831.50
TOTAL
4,60,914.06
Add 1 % Water charges on “W”
+4,609.14
TOTAL
4,65,523.20
Add GST on “X” (multiplying factor 0.2127)
+99,016.78
TOTAL
5,64,539.98
Add 15% CPOH on “Y”
+84,681.00
TOTAL
6,49,220.98
Add Cess @ 1% on “Z”
+6,492.21
Cost for 225 cum(450 Tonne)
6,55,713.19
Cost per cum.
2,914.28
SAY
₹2,914.30
D-02/SOURCEPRINTED PAGE 1262
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1262

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1262. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.