Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means)
- Item number
- 16.77
- Analysis basis
- 100 sqm
- Priced inputs
- 5
- Derived rate
- ₹7.00/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.77 (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means)) is derived from 5 priced inputs for 100 sqm and works out to ₹7.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0128 | LAB | Mate | day | 0.01 | 816.00 | 8.16 |
| 0114 | LAB | Beldar | day | 0.25 | 736.00 | 184.00 |
| 0038 | MACH | Tractor with ripper attachment.Tractor with ripper attachment | day | 0.01 | 1,350.00 | 13.50 |
| 0014 | MACH | Front end loader capacity 1.00 cum | day | 0.025 | 6,700.00 | 167.50 |
| 0017 | MACH | Hire and running charges of tipper | day | 0.028 | 4,200.00 | 117.60 |
- TOTAL
- 490.76
- Add 1 % Water charges on “W”
- +4.91
- TOTAL
- 495.67
- Add GST on “X” (multiplying factor 0.2127)
- +105.43
- TOTAL
- 601.10
- Add 15% CPOH on “Y”
- +90.17
- TOTAL
- 691.27
- Add Cess @ 1% on “Z”
- +6.91
- Cost for 100 sqm
- 698.18
- Cost for 1 sqm
- 6.98
- SAY
- ₹7.00
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1259
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1259. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.