Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means)

Item number
16.77
Analysis basis
100 sqm
Priced inputs
5
Derived rate
₹7.00/ SQM
D-01/RATE ANALYSISITEM 16.77

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.77 (Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means)) is derived from 5 priced inputs for 100 sqm and works out to ₹7.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 16.77DETAILS OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0128LABMateday0.01816.008.16
0114LABBeldarday0.25736.00184.00
0038MACHTractor with ripper attachment.Tractor with ripper attachmentday0.011,350.0013.50
0014MACHFront end loader capacity 1.00 cumday0.0256,700.00167.50
0017MACHHire and running charges of tipperday0.0284,200.00117.60
BUILD-UP TO RATE
TOTAL
490.76
Add 1 % Water charges on “W”
+4.91
TOTAL
495.67
Add GST on “X” (multiplying factor 0.2127)
+105.43
TOTAL
601.10
Add 15% CPOH on “Y”
+90.17
TOTAL
691.27
Add Cess @ 1% on “Z”
+6.91
Cost for 100 sqm
698.18
Cost for 1 sqm
6.98
SAY
₹7.00
D-02/SOURCEPRINTED PAGE 1259
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1259

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1259. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.