CPWD Analysis of Rates · Road Work

Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means)

Item number
16.77
Analysis basis
Details of cost for 100 sqm
Priced inputs
5
Derived rate
7.00 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.77 Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material within all lifts and lead upto 1km (by mechanical means) — is derived from 5 priced inputs for 100 sqm and works out to ₹7.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0128MateLabourday0.01816.008.16
0114BeldarLabourday0.25736.00184.00
0038Tractor with ripper attachment.Tractor with ripper attachmentMachineryday0.011,350.0013.50
0014Front end loader capacity 1.00 cumMachineryday0.0256,700.00167.50
0017Hire and running charges of tipperMachineryday0.0284,200.00117.60
TOTAL
490.76
Add 1 % Water charges on “W”
4.91
TOTAL
495.67
Add GST on “X” (multiplying factor 0.2127)
105.43
TOTAL
601.10
Add 15% CPOH on “Y”
90.17
TOTAL
691.27
Add Cess @ 1% on “Z”
6.91
Cost for 100 sqm
698.18
Cost for 1 sqm
6.98
Say
7.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1259. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.