Deduct for using of M-20 grade concrete instead of M-25 grade concrete in C.C. pavement

Item number
16.76
Analysis basis
1 cum
Priced inputs
2
Derived rate
₹203.80/ CUM
D-01/RATE ANALYSISITEM 16.76

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.76 (Deduct for using of M-20 grade concrete instead of M-25 grade concrete in C.C. pavement) is derived from 2 priced inputs for 1 cum and works out to ₹203.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Cement for M-25 mix = 0.410 t
  • Cement for M - 20 mix = 0.383 t
  • Difference = 0.027 t
  • METERIAL
ANALYSIS OF RATES · ITEM 16.76DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0367MATPortland Cement (OPC-43 grade)tonne0.0275,156.00139.21
7318MATPlasticizer / super plasticizerkilogram0.13530.004.05
BUILD-UP TO RATE
TOTAL
143.26
Add 1 % Water charges on “W”
+1.43
TOTAL
144.69
Add GST on “X” (multiplying factor 0.2127)
+30.78
TOTAL
175.47
Add 15% CPOH on “Y”
+26.32
TOTAL
201.79
Add Cess @ 1% on “Z”
+2.02
Cost for 1 cum.
203.81
SAY
₹203.80
D-02/SOURCEPRINTED PAGE 1258
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1258

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1258. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.