Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately)
- Item number
- 16.75
- Analysis basis
- 1.00 cum
- Priced inputs
- 3
- Derived rate
- ₹9,823.80/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.75 (Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately)) is derived from 3 priced inputs for 1.00 cum and works out to ₹9,823.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Ready mix concrete M 25 = 1.00 cum. i/c
- placing of concrete, vibrating, leveling etc
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per Item No.5.33.1.1 of SH:RCCRate as per item 5.33.1.1 | cum | 1 | 9,504.75 | 9,504.75 | |
| 9999 | MAT | Operational charges for vacuum dewatering system i/c screed vibration, placing of filter mat , top mat, vacuum process, floating , troweling, Brooming etc | L.S. | 57.2 | 2.27 | 129.84 |
| 9999 | MAT | T& P charges i/c consumable power charges, loading , unloading and hire charges of equipments | L.S. | 41.6 | 2.27 | 94.43 |
- TOTAL
- 9,729.02
- Add 1 % Water charges on “W-A”
- +2.24
- TOTAL
- 9,731.26
- Add GST on “X-A” (multiplying factor 0.2127)
- +48.18
- TOTAL
- 9,779.44
- Add 15% CPOH on “Y-A”
- +41.20
- TOTAL
- 9,820.64
- Add Cess @ 1% on “Z-A”
- +3.16
- Cost for 1 cum
- 9,823.80
- Cost for 1 cum
- 9,823.80
- SAY
- ₹9,823.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1258
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1258. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.