Skip to main content

CPWD Analysis of Rates · Road Work

Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately)

Item number
16.75
Analysis basis
Details of cost for 1.00 cum
Priced inputs
3
Derived rate
9,823.80 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.75 Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately) — is derived from 3 priced inputs for 1.00 cum and works out to ₹9,823.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Ready mix concrete M 25 = 1.00 cum. i/c
  • placing of concrete, vibrating, leveling etc
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per Item No.5.33.1.1 of SH:RCCRate as per item 5.33.1.1Sub-analysiscum19,504.759,504.75
9999Operational charges for vacuum dewatering system i/c screed vibration, placing of filter mat , top mat, vacuum process, floating , troweling, Brooming etcMaterialL.S.57.22.27129.84
9999T& P charges i/c consumable power charges, loading , unloading and hire charges of equipmentsMaterialL.S.41.62.2794.43
TOTAL
9,729.02
Add 1 % Water charges on “W-A”
2.24
TOTAL
9,731.26
Add GST on “X-A” (multiplying factor 0.2127)
48.18
TOTAL
9,779.44
Add 15% CPOH on “Y-A”
41.20
TOTAL
9,820.64
Add Cess @ 1% on “Z-A”
3.16
Cost for 1 cum
9,823.80
Cost for 1 cum
9,823.80
Say
9,823.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1258. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works