Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately)

Item number
16.75
Analysis basis
1.00 cum
Priced inputs
3
Derived rate
₹9,823.80/ CUM
D-01/RATE ANALYSISITEM 16.75

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.75 (Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in-charge. (The panel shuttering work shall be paid for separately). (Note:- Cement content considered in this item is @ 330 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately)) is derived from 3 priced inputs for 1.00 cum and works out to ₹9,823.80 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Ready mix concrete M 25 = 1.00 cum. i/c
  • placing of concrete, vibrating, leveling etc
ANALYSIS OF RATES · ITEM 16.75DETAILS OF COST FOR 1.00 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per Item No.5.33.1.1 of SH:RCCRate as per item 5.33.1.1cum19,504.759,504.75
9999MATOperational charges for vacuum dewatering system i/c screed vibration, placing of filter mat , top mat, vacuum process, floating , troweling, Brooming etcL.S.57.22.27129.84
9999MATT& P charges i/c consumable power charges, loading , unloading and hire charges of equipmentsL.S.41.62.2794.43
BUILD-UP TO RATE
TOTAL
9,729.02
Add 1 % Water charges on “W-A”
+2.24
TOTAL
9,731.26
Add GST on “X-A” (multiplying factor 0.2127)
+48.18
TOTAL
9,779.44
Add 15% CPOH on “Y-A”
+41.20
TOTAL
9,820.64
Add Cess @ 1% on “Z-A”
+3.16
Cost for 1 cum
9,823.80
Cost for 1 cum
9,823.80
SAY
₹9,823.80
D-02/SOURCEPRINTED PAGE 1258
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1258

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1258. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.