75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with

Stone aggregate 40 mm nominal size
Item number
16.74.3
Analysis basis
100 sqm
Priced inputs
3
Derived rate
₹172.35/ SQM
D-01/RATE ANALYSISITEM 16.74.3

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.74.3 (75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with : Stone aggregate 40 mm nominal size) is derived from 3 priced inputs for 100 sqm and works out to ₹172.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 100sqm x7.50cm= 7.50 cum
ANALYSIS OF RATES · ITEM 16.74.3DETAIL OF COST FOR 100 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0293MATStone Aggregate (Single size) : 40 mm nominal sizecum7.51,400.0010,500.00
0114LABBeldarday2.05736.001,508.80
0101LABBhistiday0.13816.00106.08
BUILD-UP TO RATE
TOTAL
12,114.88
Add 1 % Water charges on “W”
+121.15
TOTAL
12,236.03
Add GST on “X” (multiplying factor 0.2127)
+2,602.60
TOTAL
14,838.63
Add 15% CPOH on “Y”
+2,225.79
TOTAL
17,064.42
Add Cess @ 1% on “Z”
+170.64
Cost for 100 sqm
17,235.06
Cost per sqm
172.35
SAY
₹172.35
D-02/SOURCEPRINTED PAGE 1257
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1257

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1257. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.