75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with

Stone aggregate 20 mm nominal size

Item number
16.74.2
Analysis basis
Detail of cost for 100 sqm
Priced inputs
3
Derived rate
175.00 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.74.2 75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with : Stone aggregate 20 mm nominal size — is derived from 3 priced inputs for 100 sqm and works out to ₹175.00 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 100sqm x7.50cm= 7.50 cum
CodeInputUnitQuantityRate (INR)Amount (INR)
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum7.51,425.0010,687.50
0114BeldarLabourday2.05736.001,508.80
0101BhistiLabourday0.13816.00106.08
TOTAL
12,302.38
Add 1 % Water charges on “W”
123.02
TOTAL
12,425.40
Add GST on “X” (multiplying factor 0.2127)
2,642.88
TOTAL
15,068.28
Add 15% CPOH on “Y”
2,260.24
TOTAL
17,328.52
Add Cess @ 1% on “Z”
173.29
Cost for 100 sqm
17,501.81
Cost per sqm
175.02
Say
175.00

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1257. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.