Skip to main content

CPWD Analysis of Rates · Road Work

75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with

Moorum

Item number
16.74.1
Analysis basis
Details of cost for 100 sqm
Priced inputs
3
Derived rate
76.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.74.1 75 mm thick back filling for pitching including supplying of required materials and consolidation etc. complete with : Moorum — is derived from 3 priced inputs for 100 sqm and works out to ₹76.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • Carriage by mechanical transport i/c loading
  • unloading and stacking
CodeInputUnitQuantityRate (INR)Amount (INR)
0810MoorumMaterialcum7.5540.004,050.00
0114BeldarLabourday1.64736.001,207.04
0101BhistiLabourday0.13816.00106.08
TOTAL
5,363.12
Add 1 % Water charges on “W”
53.63
TOTAL
5,416.75
Add GST on “X” (multiplying factor 0.2127)
1,152.14
TOTAL
6,568.89
Add 15% CPOH on “Y”
985.33
TOTAL
7,554.22
Add Cess @ 1% on “Z”
75.54
Cost for 100 sqm
7,629.76
Cost per sqm
76.30
Say
76.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1256. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works