Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately)

Item number
16.73
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹659.05/ SQM
D-01/RATE ANALYSISITEM 16.73

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.73 (Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately)) is derived from 5 priced inputs for 10 sqm and works out to ₹659.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

ANALYSIS OF RATES · ITEM 16.73DETAIL OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0123LABMason 1st classMason 1st classday1.08897.00968.76
0124LABMason 2nd classMason 2nd classday1.08816.00881.28
0114LABBeldarday2.15736.001,582.40
0115LABCoolieday1.61736.001,184.96
9999MATSundriesL.S.6.762.2715.35
BUILD-UP TO RATE
TOTAL
4,632.75
Add 1 % Water charges on “W”
+46.33
TOTAL
4,679.08
Add GST on “X” (multiplying factor 0.2127)
+995.24
TOTAL
5,674.32
Add 15% CPOH on “Y”
+851.15
TOTAL
6,525.47
Add Cess @ 1% on “Z”
+65.25
Cost for 10 sqm
6,590.72
Cost for one sqm
659.07
SAY
₹659.05
D-02/SOURCEPRINTED PAGE 1256
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1256

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1256. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.