CPWD Analysis of Rates · Road Work
Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately)
- Item number
- 16.73
- Analysis basis
- Detail of cost for 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹659.05 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.73 — Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately) — is derived from 5 priced inputs for 10 sqm and works out to ₹659.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0123 | Mason 1st classMason 1st classLabour | day | 1.08 | 897.00 | 968.76 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1.08 | 816.00 | 881.28 |
| 0114 | BeldarLabour | day | 2.15 | 736.00 | 1,582.40 |
| 0115 | CoolieLabour | day | 1.61 | 736.00 | 1,184.96 |
| 9999 | SundriesMaterial | L.S. | 6.76 | 2.27 | 15.35 |
- TOTAL
- 4,632.75
- Add 1 % Water charges on “W”
- 46.33
- TOTAL
- 4,679.08
- Add GST on “X” (multiplying factor 0.2127)
- 995.24
- TOTAL
- 5,674.32
- Add 15% CPOH on “Y”
- 851.15
- TOTAL
- 6,525.47
- Add Cess @ 1% on “Z”
- 65.25
- Cost for 10 sqm
- 6,590.72
- Cost for one sqm
- 659.07
- Say
- 659.05
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1256. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.