Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately)
- Item number
- 16.73
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹659.05/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.73 (Dry stone pitching 22.5 cm thick laid in courses and required profile with hammer dressed stones having no side less than 15 cm, with minimum depth of 20 cm including preparing the bedding surface etc. all complete. (Payment for Stone to be made separately)) is derived from 5 priced inputs for 10 sqm and works out to ₹659.05 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0123 | LAB | Mason 1st classMason 1st class | day | 1.08 | 897.00 | 968.76 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1.08 | 816.00 | 881.28 |
| 0114 | LAB | Beldar | day | 2.15 | 736.00 | 1,582.40 |
| 0115 | LAB | Coolie | day | 1.61 | 736.00 | 1,184.96 |
| 9999 | MAT | Sundries | L.S. | 6.76 | 2.27 | 15.35 |
- TOTAL
- 4,632.75
- Add 1 % Water charges on “W”
- +46.33
- TOTAL
- 4,679.08
- Add GST on “X” (multiplying factor 0.2127)
- +995.24
- TOTAL
- 5,674.32
- Add 15% CPOH on “Y”
- +851.15
- TOTAL
- 6,525.47
- Add Cess @ 1% on “Z”
- +65.25
- Cost for 10 sqm
- 6,590.72
- Cost for one sqm
- 659.07
- SAY
- ₹659.05
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1256
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1256. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.