CPWD Analysis of Rates · Road Work

Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge

Made of G.I. wire of dia. 4 mm, PVC coated to achieve outer dia not less than 5 mm in required colour and shade

Item number
16.70.2
Analysis basis
Details of cost for 10 sqm.
Priced inputs
5
Derived rate
1,067.10 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.70.2 Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge Made of G.I. wire of dia. 4 mm, PVC coated to achieve outer dia not less than 5 mm in required colour and shade — is derived from 5 priced inputs for 10 sqm and works out to ₹1,067.10 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • G.I. chain link 50x50 mm mesh PVC coated
  • = 10.00 sqm.
  • Wastage @ 5% = 0.50 sqm.
  • Total = 10.50 sqm.
CodeInputUnitQuantityRate (INR)Amount (INR)
8696Chain link fabric fencing mesh of size 50x50 mm made of G.I. wire of dia 4 mm, PVC coated to outer dia 5 mmMaterialsqm10.5363.003,811.50
9977Carriage.MaterialL.S.1562.27354.12
0103Blacksmith 2nd classLabourday2.14816.001,746.24
0114BeldarLabourday1.62736.001,192.32
9999Sundries including G.I. wire, nuts and bolts and warshersMaterialL.S.174.752.27396.68
TOTAL
7,500.86
Add 1 % Water charges on “W”
75.01
TOTAL
7,575.87
Add GST on “X” (multiplying factor 0.2127)
1,611.39
TOTAL
9,187.26
Add 15% CPOH on “Y”
1,378.09
TOTAL
10,565.35
Add Cess @ 1% on “Z”
105.65
Cost for 10 sqm.
10,671.00
Cost for 1 sqm.
1,067.10
Say
1,067.10

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1254. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works