Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge
- Item number
- 16.70.1
- Analysis basis
- 10 sqm
- Priced inputs
- 5
- Derived rate
- ₹1,017.80/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.70.1 (Providing and fixing G.I. chain link fabric fencing of required width in mesh size 50x50 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge Made of G.I. wire of dia 4 mm) is derived from 5 priced inputs for 10 sqm and works out to ₹1,017.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- G.I. chain link 50x50 mm mesh = 10.00
- sqm.
- Wastage @ 5% = 0.50 sqm.
- Total = 10.50 sqm.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8695 | MAT | Chain link fabric fencing mesh of size 50x50 mm made of G.I. wire of dia 4 mm | sqm | 10.5 | 330.00 | 3,465.00 |
| 9977 | MAT | Carriage. | L.S. | 156 | 2.27 | 354.12 |
| 0103 | LAB | Blacksmith 2nd class | day | 2.14 | 816.00 | 1,746.24 |
| 0114 | LAB | Beldar | day | 1.62 | 736.00 | 1,192.32 |
| 9999 | MAT | Sundries including G.I. wire, nuts and bolts and warshers | L.S. | 174.75 | 2.27 | 396.68 |
- TOTAL
- 7,154.36
- Add 1 % Water charges on “W”
- +71.54
- TOTAL
- 7,225.90
- Add GST on “X” (multiplying factor 0.2127)
- +1,536.95
- TOTAL
- 8,762.85
- Add 15% CPOH on “Y”
- +1,314.43
- TOTAL
- 10,077.28
- Add Cess @ 1% on “Z”
- +100.77
- Cost for 10 sqm.
- 10,178.05
- Cost for 1 sqm.
- 1,017.81
- SAY
- ₹1,017.80
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1253
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1253. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.