CPWD Analysis of Rates · Road Work
Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge)
- Item number
- 16.69
- Analysis basis
- Details of cost 100 metre i.e.
- Priced inputs
- 6
- Derived rate
- ₹10,117.60
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.69 — Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge) — is derived from 6 priced inputs and works out to ₹10,117.60 after water charges, GST, CPOH and cess. The full build-up is below.
- 100x0.375x0.20=7.50 cum.
- No. of kerb stones = 100/0.405=247 Nos
- Precast C.C. Kerb stone M - 25 =
- 247x0.40x0.375x0.20=7.41 cum
- METERIAL
- Mortar 1:3 for fixing joints =
- 246x1x[(0.115+0.20)/2] x 0.375x0.005 =
- 0.073 cum.
- Cement mortar 1:3 (1 cement : 3 coarse
- sand)
- Labour for fixing of kerb stones
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 8686 | Precast C.C. Kerb stone M - 25 (including carriage)Material | cum | 7.41 | 6,160.00 | 45,645.60 |
| Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysis | cum | 0.073 | 4,881.95 | 356.38 | |
| 0123 | Mason 1st classMason 1st classLabour | day | 2.5 | 897.00 | 2,242.50 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 2.5 | 816.00 | 2,040.00 |
| 0114 | BeldarLabour | day | 2.5 | 736.00 | 1,840.00 |
| 0115 | CoolieLabour | day | 1.65 | 736.00 | 1,214.40 |
- TOTAL
- 53,338.88
- Add 1 % Water charges on “W”
- 533.39
- TOTAL
- 53,872.27
- Add GST on “X” (multiplying factor 0.2127)
- 11,458.63
- TOTAL
- 65,330.90
- Add 15% CPOH on “Y”
- 9,799.64
- TOTAL
- 75,130.54
- Add Cess @ 1% on “Z”
- 751.31
- Cost of 7.50 cum
- 75,881.85
- cost for 1 cum.
- 10,117.58
- Say
- 10,117.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1253. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.