Skip to main content
R/DAR 2023

Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge)

Item number
16.69
Analysis basis
Details of cost 100 metre i.e.
Priced inputs
6
Derived rate
₹10,117.60
D-01/RATE ANALYSISITEM 16.69

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.69 (Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge)) is derived from 6 priced inputs and works out to ₹10,117.60 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 100x0.375x0.20=7.50 cum.
  • No. of kerb stones = 100/0.405=247 Nos
  • Precast C.C. Kerb stone M - 25 =
  • 247x0.40x0.375x0.20=7.41 cum
  • METERIAL
  • Mortar 1:3 for fixing joints =
  • 246x1x[(0.115+0.20)/2] x 0.375x0.005 =
  • 0.073 cum.
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • Labour for fixing of kerb stones
ANALYSIS OF RATES · ITEM 16.69DETAILS OF COST 100 METRE I.E
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8686MATPrecast C.C. Kerb stone M - 25 (including carriage)cum7.416,160.0045,645.60
SUBRate as per Item Number 3.8 of SH: MortarsRate as per item 3.8cum0.0734,881.95356.38
0123LABMason 1st classMason 1st classday2.5897.002,242.50
0124LABMason 2nd classMason 2nd classday2.5816.002,040.00
0114LABBeldarday2.5736.001,840.00
0115LABCoolieday1.65736.001,214.40
BUILD-UP TO RATE
TOTAL
53,338.88
Add 1 % Water charges on “W”
+533.39
TOTAL
53,872.27
Add GST on “X” (multiplying factor 0.2127)
+11,458.63
TOTAL
65,330.90
Add 15% CPOH on “Y”
+9,799.64
TOTAL
75,130.54
Add Cess @ 1% on “Z”
+751.31
Cost of 7.50 cum
75,881.85
cost for 1 cum.
10,117.58
SAY
₹10,117.60
D-02/SOURCEPRINTED PAGE 1253
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1253

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1253. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.