CPWD Analysis of Rates · Road Work

Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge)

Item number
16.69
Analysis basis
Details of cost 100 metre i.e.
Priced inputs
6
Derived rate
10,117.60

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.69 Providing and laying at or near ground level factory made kerb stone of M-25 grade cement concrete in position to the required line, level and curvature, jointed with cement mortar 1:3 (1 cement: 3 coarse sand), including making joints with or without grooves (thickness of joints except at sharp curve shall not to more than 5mm), including making drainage opening wherever required complete etc. as per direction of Engineer-in-charge (length of finished kerb edging shall be measured to calculate volume for payment). (Precast C.C. kerb stone shall be approved by Engineer-in-charge) — is derived from 6 priced inputs and works out to ₹10,117.60 after water charges, GST, CPOH and cess. The full build-up is below.

  • 100x0.375x0.20=7.50 cum.
  • No. of kerb stones = 100/0.405=247 Nos
  • Precast C.C. Kerb stone M - 25 =
  • 247x0.40x0.375x0.20=7.41 cum
  • METERIAL
  • Mortar 1:3 for fixing joints =
  • 246x1x[(0.115+0.20)/2] x 0.375x0.005 =
  • 0.073 cum.
  • Cement mortar 1:3 (1 cement : 3 coarse
  • sand)
  • Labour for fixing of kerb stones
CodeInputUnitQuantityRate (INR)Amount (INR)
8686Precast C.C. Kerb stone M - 25 (including carriage)Materialcum7.416,160.0045,645.60
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.0734,881.95356.38
0123Mason 1st classMason 1st classLabourday2.5897.002,242.50
0124Mason 2nd classMason 2nd classLabourday2.5816.002,040.00
0114BeldarLabourday2.5736.001,840.00
0115CoolieLabourday1.65736.001,214.40
TOTAL
53,338.88
Add 1 % Water charges on “W”
533.39
TOTAL
53,872.27
Add GST on “X” (multiplying factor 0.2127)
11,458.63
TOTAL
65,330.90
Add 15% CPOH on “Y”
9,799.64
TOTAL
75,130.54
Add Cess @ 1% on “Z”
751.31
Cost of 7.50 cum
75,881.85
cost for 1 cum.
10,117.58
Say
10,117.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1253. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.