Providing and fixing G.I. chain link fabric fencing of required width in mesh size 25x25 mm made of G.I. wire of dia 3 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge

Item number
16.71
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹1,149.25/ SQM
D-01/RATE ANALYSISITEM 16.71

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.71 (Providing and fixing G.I. chain link fabric fencing of required width in mesh size 25x25 mm made of G.I. wire of dia 3 mm including strengthening with 2 mm dia wire or nuts, bolts and washers as required complete as per the direction of Engineer-in-charge) is derived from 5 priced inputs for 10 sqm and works out to ₹1,149.25 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • G.I. chain link 25x25 mm mesh = 10.00
  • sqm.
  • Wastage @ 5% = 0.50 sqm.
  • Total = 10.50 sqm.
ANALYSIS OF RATES · ITEM 16.71DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8697MATChain link fabric fencing mesh of size 25x25 mm made of G.I. wire of dia 3 mmsqm10.5418.004,389.00
9977MATCarriage.L.S.1562.27354.12
0103LABBlacksmith 2nd classday2.14816.001,746.24
0114LABBeldarday1.62736.001,192.32
9999MATSundries including G.I. wire, nuts and bolts and warshersL.S.174.752.27396.68
BUILD-UP TO RATE
TOTAL
8,078.36
Add 1 % Water charges on “W”
+80.78
TOTAL
8,159.14
Add GST on “X” (multiplying factor 0.2127)
+1,735.45
TOTAL
9,894.59
Add 15% CPOH on “Y”
+1,484.19
TOTAL
11,378.78
Add Cess @ 1% on “Z”
+113.79
Cost for 10 sqm.
11,492.57
Cost for 1 sqm.
1,149.26
SAY
₹1,149.25
D-02/SOURCEPRINTED PAGE 1255
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1255

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1255. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate