Excavating holes upto 0.10 cum, including getting out the excavated soil, then returning the soil as deported in layers not exceeding 20 cm in depth, including consolidating and deposited layer by ramming watering etc., disposing of surplus excavated soil as directed with in a lead of 50 mm and lift upto 1.5 m

All kind of soil
Item number
16.66.1
Analysis basis
30 holes
Priced inputs
2
Derived rate
₹27.50/ HOLE
D-01/RATE ANALYSISITEM 16.66.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.66.1 (Excavating holes upto 0.10 cum, including getting out the excavated soil, then returning the soil as deported in layers not exceeding 20 cm in depth, including consolidating and deposited layer by ramming watering etc., disposing of surplus excavated soil as directed with in a lead of 50 mm and lift upto 1.5 m All kind of soil) is derived from 2 priced inputs for 30 holes and works out to ₹27.50 per hole after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Earth work 30x0.10 = 3.0 cum.
  • Extra labour for filling and ramming
ANALYSIS OF RATES · ITEM 16.66.1DETAILS OF COST FOR 30 HOLES-
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per item no. 2.8.1 of SH: Earth workRate as per item 2.8.1cum3260.30780.90
9999MATSundriesL.S.13.522.2730.69
BUILD-UP TO RATE
TOTAL
811.59
Add 1 % Water charges on “W-A”
+0.31
TOTAL
811.90
Add GST on “X-A” (multiplying factor 0.2127)
+6.59
TOTAL
818.49
Add 15% CPOH on “Y-A”
+5.64
TOTAL
824.13
Add Cess @ 1% on “Z-A”
+0.43
Cost of 30 holes
824.56
Cost of 1 hole
27.49
SAY
₹27.50
D-02/SOURCEPRINTED PAGE 1251
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1251

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1251. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.