Skip to main content

CPWD Analysis of Rates · Road Work

Providing and fixing post delineators made of ABS round body fitted with 2 nos 100 mm dia high reflective reflectors and mounted on MS pipe of 65 mm dia duly powder coated anti-rust and anti theft steel to be installed as per direction of Engineer-in-charge

Item number
16.65
Analysis basis
Details of cost for 1 no.
Priced inputs
3
Derived rate
904.20 / no

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.65 Providing and fixing post delineators made of ABS round body fitted with 2 nos 100 mm dia high reflective reflectors and mounted on MS pipe of 65 mm dia duly powder coated anti-rust and anti theft steel to be installed as per direction of Engineer-in-charge — is derived from 3 priced inputs for 1 no and works out to ₹904.20 per no after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
8685DelineatorMaterialeach1370.00370.00
9999Fixing materials.MaterialL.S.782.27177.06
9999Fixing charges.MaterialL.S.392.2788.53
TOTAL
635.59
Add 1 % Water charges on “W”
6.36
TOTAL
641.95
Add GST on “X” (multiplying factor 0.2127)
136.54
TOTAL
778.49
Add 15% CPOH on “Y”
116.77
TOTAL
895.26
Add Cess @ 1% on “Z”
8.95
Cost of 1 no.
904.21
Say
904.20

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1250. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works