Providing and laying 75 mm thick compacted bed of dry brick aggregate of 40 mm thick nominal size including spreading, well ramming, consolidating and grouting with jamuna sand, including finishing smooth etc. complete as per direction of Engineer-in-charge

Item number
16.64
Analysis basis
10 sqm
Priced inputs
5
Derived rate
₹199.35/ SQM
D-01/RATE ANALYSISITEM 16.64

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.64 (Providing and laying 75 mm thick compacted bed of dry brick aggregate of 40 mm thick nominal size including spreading, well ramming, consolidating and grouting with jamuna sand, including finishing smooth etc. complete as per direction of Engineer-in-charge) is derived from 5 priced inputs for 10 sqm and works out to ₹199.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • METERIAL
ANALYSIS OF RATES · ITEM 16.64DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0287MATBrick Aggregate (Single size) : 40 mm nominal sizecum1700.00700.00
6501MATSand zone V (Jamuna)cum0.081,320.00105.60
0114LABBeldarday0.35736.00257.60
0115LABCoolieday0.26736.00191.36
0101LABBhistiday0.18816.00146.88
BUILD-UP TO RATE
TOTAL
1,401.44
Add 1 % Water charges on “W”
+14.01
TOTAL
1,415.45
Add GST on “X” (multiplying factor 0.2127)
+301.07
TOTAL
1,716.52
Add 15% CPOH on “Y”
+257.48
TOTAL
1,974.00
Add Cess @ 1% on “Z”
+19.74
Cost for 10 sqm.
1,993.74
Cost for 1 sqm.
199.37
SAY
₹199.35
D-02/SOURCEPRINTED PAGE 1250
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1250

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1250. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.