CPWD Analysis of Rates · Road Work
Providing and laying 75 mm thick compacted bed of dry brick aggregate of 40 mm thick nominal size including spreading, well ramming, consolidating and grouting with jamuna sand, including finishing smooth etc. complete as per direction of Engineer-in-charge
- Item number
- 16.64
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 5
- Derived rate
- ₹199.35 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.64 — Providing and laying 75 mm thick compacted bed of dry brick aggregate of 40 mm thick nominal size including spreading, well ramming, consolidating and grouting with jamuna sand, including finishing smooth etc. complete as per direction of Engineer-in-charge — is derived from 5 priced inputs for 10 sqm and works out to ₹199.35 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- METERIAL
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0287 | Brick Aggregate (Single size) : 40 mm nominal sizeMaterial | cum | 1 | 700.00 | 700.00 |
| 6501 | Sand zone V (Jamuna)Material | cum | 0.08 | 1,320.00 | 105.60 |
| 0114 | BeldarLabour | day | 0.35 | 736.00 | 257.60 |
| 0115 | CoolieLabour | day | 0.26 | 736.00 | 191.36 |
| 0101 | BhistiLabour | day | 0.18 | 816.00 | 146.88 |
- TOTAL
- 1,401.44
- Add 1 % Water charges on “W”
- 14.01
- TOTAL
- 1,415.45
- Add GST on “X” (multiplying factor 0.2127)
- 301.07
- TOTAL
- 1,716.52
- Add 15% CPOH on “Y”
- 257.48
- TOTAL
- 1,974.00
- Add Cess @ 1% on “Z”
- 19.74
- Cost for 10 sqm.
- 1,993.74
- Cost for 1 sqm.
- 199.37
- Say
- 199.35
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1250. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.