CPWD Analysis of Rates · Road Work
Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-incharge
- Item number
- 16.63
- Analysis basis
- Details of cost for 10 sqm.
- Priced inputs
- 6
- Derived rate
- ₹558.30 / sqm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.63 — Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-incharge — is derived from 6 priced inputs for 10 sqm and works out to ₹558.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- METERIAL
- Cement concrete-1:3:6
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0287 | Brick Aggregate (Single size) : 40 mm nominal sizeMaterial | cum | 1 | 700.00 | 700.00 |
| 6501 | Sand zone V (Jamuna)Material | cum | 0.08 | 1,320.00 | 105.60 |
| 0114 | BeldarLabour | day | 0.35 | 736.00 | 257.60 |
| 0115 | CoolieLabour | day | 0.26 | 736.00 | 191.36 |
| 0101 | BhistiLabour | day | 0.18 | 816.00 | 146.88 |
| Rate as per item no 4.1.6 of SH : Concrete WorkRate as per item 4.1.6Sub-analysis | cum | 0.5 | 7,178.75 | 3,589.38 |
- TOTAL
- 4,990.82
- Add 1 % Water charges on “W-A”
- 14.01
- TOTAL
- 5,004.83
- Add GST on “X-A” (multiplying factor 0.2127)
- 301.07
- TOTAL
- 5,305.90
- Add 15% CPOH on “Y-A”
- 257.48
- TOTAL
- 5,563.38
- Add Cess @ 1% on “Z-A”
- 19.74
- Cost for 10 sqm.
- 5,583.12
- Cost for 1 sqm.
- 558.31
- Say
- 558.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1249. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.