Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-incharge

Item number
16.63
Analysis basis
10 sqm
Priced inputs
6
Derived rate
₹558.30/ SQM
D-01/RATE ANALYSISITEM 16.63

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.63 (Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-incharge) is derived from 6 priced inputs for 10 sqm and works out to ₹558.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • METERIAL
  • Cement concrete-1:3:6
ANALYSIS OF RATES · ITEM 16.63DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0287MATBrick Aggregate (Single size) : 40 mm nominal sizecum1700.00700.00
6501MATSand zone V (Jamuna)cum0.081,320.00105.60
0114LABBeldarday0.35736.00257.60
0115LABCoolieday0.26736.00191.36
0101LABBhistiday0.18816.00146.88
SUBRate as per item no 4.1.6 of SH : Concrete WorkRate as per item 4.1.6cum0.57,178.753,589.38
BUILD-UP TO RATE
TOTAL
4,990.82
Add 1 % Water charges on “W-A”
+14.01
TOTAL
5,004.83
Add GST on “X-A” (multiplying factor 0.2127)
+301.07
TOTAL
5,305.90
Add 15% CPOH on “Y-A”
+257.48
TOTAL
5,563.38
Add Cess @ 1% on “Z-A”
+19.74
Cost for 10 sqm.
5,583.12
Cost for 1 sqm.
558.31
SAY
₹558.30
D-02/SOURCEPRINTED PAGE 1249
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1249

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1249. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.