Skip to main content

CPWD Analysis of Rates · Road Work

Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-incharge

Item number
16.63
Analysis basis
Details of cost for 10 sqm.
Priced inputs
6
Derived rate
558.30 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.63 Providing, laying and making kerb channel 30 cm wide and 50 mm thick with cement concrete 1:3:6 (1 cement: 3 coarse sand:6 graded stone aggregate 20 mm nominal size) over 75mm bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including finishing the top smooth etc. complete and as per direction of Engineer-incharge — is derived from 6 priced inputs for 10 sqm and works out to ₹558.30 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • METERIAL
  • Cement concrete-1:3:6
CodeInputUnitQuantityRate (INR)Amount (INR)
0287Brick Aggregate (Single size) : 40 mm nominal sizeMaterialcum1700.00700.00
6501Sand zone V (Jamuna)Materialcum0.081,320.00105.60
0114BeldarLabourday0.35736.00257.60
0115CoolieLabourday0.26736.00191.36
0101BhistiLabourday0.18816.00146.88
Rate as per item no 4.1.6 of SH : Concrete WorkRate as per item 4.1.6Sub-analysiscum0.57,178.753,589.38
TOTAL
4,990.82
Add 1 % Water charges on “W-A”
14.01
TOTAL
5,004.83
Add GST on “X-A” (multiplying factor 0.2127)
301.07
TOTAL
5,305.90
Add 15% CPOH on “Y-A”
257.48
TOTAL
5,563.38
Add Cess @ 1% on “Z-A”
19.74
Cost for 10 sqm.
5,583.12
Cost for 1 sqm.
558.31
Say
558.30

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1249. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works