Providing and applying 2.5 mm thick road marking strips (retroreflective) of specified shade/ colour using hot thermoplastic material by fully/ semi automatic thermoplastic paint applicator machine fitted with profile shoe, glass beads dispenser, propane tank heater and profile shoe heater, driven by experienced operator on road surface including cost of material, labour, T&P, cleaning the road surface of all dirt, seals, oil, grease and foreign material etc. complete as per direction of Engineer-in-charge and accordance with applicable specifications

Item number
16.62
Analysis basis
Details of cost for 200 sqm (Area covered
Priced inputs
8
Derived rate
747.80 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.62 Providing and applying 2.5 mm thick road marking strips (retroreflective) of specified shade/ colour using hot thermoplastic material by fully/ semi automatic thermoplastic paint applicator machine fitted with profile shoe, glass beads dispenser, propane tank heater and profile shoe heater, driven by experienced operator on road surface including cost of material, labour, T&P, cleaning the road surface of all dirt, seals, oil, grease and foreign material etc. complete as per direction of Engineer-in-charge and accordance with applicable specifications — is derived from 8 priced inputs for 200 sqm and works out to ₹747.80 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • on one day):Thermoplastic paint screeded in paint
  • form for 2.5 mm thick road making
  • stripe including glass beads etc. as per
  • specifications
  • 200 sqm @ 5kg/ sqm = 1000 kg
  • Wastage @ 5% = 50kg
  • Total = 1050 kg
  • Glass beads (B-class) to be sprayed over
  • the paint stripe @ 250 gms. Per sqm =
  • 100x0.25=25 kg
CodeInputUnitQuantityRate (INR)Amount (INR)
8687Thermoplastic paintMaterialkg1,05073.0076,650.00
8688Glass beadsMaterialkg5077.503,875.00
0033Paint applicator.Paint applicatorMachineryday1900.00900.00
0083Hire charges of TATA 407 or equivalent for local shiftingHire charges of TATA 407 or equivalent for local shifting.Machineryday11,550.001,550.00
1241Commercial LPG in cylinder.Commercial LPG in cylinderMaterialkg142106.0015,052.00
0157Operator (Pile/ Special machine)Labourday1897.00897.00
0139Skilled Beldar (for floor rubbing etc.)Labourday4816.003,264.00
0114BeldarLabourday4736.002,944.00
TOTAL
1,05,132.00
Add 1 % Water charges on “W”
1,051.32
TOTAL
1,06,183.32
Add GST on “X” (multiplying factor 0.2127)
22,585.19
TOTAL
1,28,768.51
Add 15% CPOH on “Y”
19,315.28
TOTAL
1,48,083.79
Add Cess @ 1% on “Z”
1,480.84
Cost for 200 sqm
1,49,564.63
Cost per sqm
747.82
Say
747.80

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1248. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works