Providing Retro-reflective regulatory sign board of size 900 mm dia metre made out of 2 mm thick aluminium sheet, face to be fully covered with high intensity encapsulated lens type retro -reflective sheeting as approved by Engineer-in-charge . Letter, symbols, borders etc. will be as per IRC - 67 with required colour scheme on the boards and with the high intensity grade A. The aluminium sheet to be riveted to M.S. frame of angle iron of size 40x40x4 mm. The boards will be fixed to 1 No. 50x50 mm square post made of M.S. angle 50x50x4 mm, 4 m long welded to the frame with adequate anti-theft arrangement .Sheet work to be painted with two or more coats of synthetic enamel paint over an under coat (primer) and back side of aluminium sheet to be painted with two or more coats of epoxy paint including appropriate priming coat complete in all respects as per direction of Engineer-in-charge

Item number
16.61
Priced inputs
9
Derived rate
₹8,154.35/ BOARD
D-01/RATE ANALYSISITEM 16.61

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.61 (Providing Retro-reflective regulatory sign board of size 900 mm dia metre made out of 2 mm thick aluminium sheet, face to be fully covered with high intensity encapsulated lens type retro -reflective sheeting as approved by Engineer-in-charge . Letter, symbols, borders etc. will be as per IRC - 67 with required colour scheme on the boards and with the high intensity grade A. The aluminium sheet to be riveted to M.S. frame of angle iron of size 40x40x4 mm. The boards will be fixed to 1 No. 50x50 mm square post made of M.S. angle 50x50x4 mm, 4 m long welded to the frame with adequate anti-theft arrangement .Sheet work to be painted with two or more coats of synthetic enamel paint over an under coat (primer) and back side of aluminium sheet to be painted with two or more coats of epoxy paint including appropriate priming coat complete in all respects as per direction of Engineer-in-charge) is derived from 9 priced inputs and works out to ₹8,154.35 per board after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Details cost for one board of 0.635 sqm
  • Aluminium sheet 2mm thick = 0.635 sqm.
  • + 0.06 = 0.695 sqm. Say 0.70 sqm @ 5.6kg/
  • sqm = 3.98 kg
  • high intensity sheet for lettering/ sing and
  • border etc Taking 40% Area=0.28 sqm, total
  • = 0.70 + 0.28 = 0.98 sqm.
  • Angle iron 40x40x4mm = 4x0.60=2.40@
  • 2.4kg/ mtr = 5.76 kg
  • 50x50x5 mm = 2x4m =8m @ 3kg/ mtr
  • =24.00 kg Total = 5.76 + 24.00 = 29.76 kg
  • (e) Painting with synthetic enamel paint
  • 1x2.40.12=0.29 sqm
  • 1x4.00x0.12=0.80 sqm,
  • Total = 0.29 + 0.80 = 1.09 sqm
  • Add 10% wastage = 0.06 sqm, total = 0.635
ANALYSIS OF RATES · ITEM 16.61
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
2704MATAluminium Strip 40 mm wide and 2 mm thickkg3.98243.00967.14
8690MATHigh intensity retro - reflective sheetHigh intensity retro - reflective sheet as per IRC 67-2001sqm0.981,345.001,318.10
SUBRate as per item no 10.2 of SH : Steel workRate as per item 10.2kg29.76133.703,978.91
0128LABMateday0.01816.008.16
0114LABBeldarday0.25736.00184.00
9999MATCost of material for drilling holes, nut bolts & rivets, facrication etcL.S.70.232.27159.42
SUBRate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1sqm1.09155.90169.93
SUBPainting with epoxy paint on back side of aluminium sheet, Rate as per Item no. 13.52.1 of SH: FinishingRate as per item 13.52.1sqm0.635241.75153.51
9999MATSundries & hole fast etc,L.S.31.22.2770.82
BUILD-UP TO RATE
TOTAL
7,009.99
Add 1% Water charges on “W-A”
+27.08
TOTAL
7,037.07
Add GST on “X-A” (multiplying factor 0.2127)
+581.67
TOTAL
7,618.74
Add 15% CPOH on “Y-A”
+497.46
TOTAL
8,116.20
Add Cess @1% on “Z-A’
+38.14
Cost of 1 board
8,154.34
Cost for 1 each
8,154.34
SAY
₹8,154.35
D-02/SOURCEPRINTED PAGE 1247
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1247

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1247. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.