Providing Retro-reflective regulatory sign board of size 900 mm dia metre made out of 2 mm thick aluminium sheet, face to be fully covered with high intensity encapsulated lens type retro -reflective sheeting as approved by Engineer-in-charge . Letter, symbols, borders etc. will be as per IRC - 67 with required colour scheme on the boards and with the high intensity grade A. The aluminium sheet to be riveted to M.S. frame of angle iron of size 40x40x4 mm. The boards will be fixed to 1 No. 50x50 mm square post made of M.S. angle 50x50x4 mm, 4 m long welded to the frame with adequate anti-theft arrangement .Sheet work to be painted with two or more coats of synthetic enamel paint over an under coat (primer) and back side of aluminium sheet to be painted with two or more coats of epoxy paint including appropriate priming coat complete in all respects as per direction of Engineer-in-charge

Item number
16.61
Priced inputs
9
Derived rate
8,154.35 / board

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.61 Providing Retro-reflective regulatory sign board of size 900 mm dia metre made out of 2 mm thick aluminium sheet, face to be fully covered with high intensity encapsulated lens type retro -reflective sheeting as approved by Engineer-in-charge . Letter, symbols, borders etc. will be as per IRC - 67 with required colour scheme on the boards and with the high intensity grade A. The aluminium sheet to be riveted to M.S. frame of angle iron of size 40x40x4 mm. The boards will be fixed to 1 No. 50x50 mm square post made of M.S. angle 50x50x4 mm, 4 m long welded to the frame with adequate anti-theft arrangement .Sheet work to be painted with two or more coats of synthetic enamel paint over an under coat (primer) and back side of aluminium sheet to be painted with two or more coats of epoxy paint including appropriate priming coat complete in all respects as per direction of Engineer-in-charge — is derived from 9 priced inputs and works out to ₹8,154.35 per board after water charges, GST, CPOH and cess. The full build-up is below.

  • Details cost for one board of 0.635 sqm
  • Aluminium sheet 2mm thick = 0.635 sqm.
  • + 0.06 = 0.695 sqm. Say 0.70 sqm @ 5.6kg/
  • sqm = 3.98 kg
  • high intensity sheet for lettering/ sing and
  • border etc Taking 40% Area=0.28 sqm, total
  • = 0.70 + 0.28 = 0.98 sqm.
  • Angle iron 40x40x4mm = 4x0.60=2.40@
  • 2.4kg/ mtr = 5.76 kg
  • 50x50x5 mm = 2x4m =8m @ 3kg/ mtr
  • =24.00 kg Total = 5.76 + 24.00 = 29.76 kg
  • (e) Painting with synthetic enamel paint
  • 1x2.40.12=0.29 sqm
  • 1x4.00x0.12=0.80 sqm,
  • Total = 0.29 + 0.80 = 1.09 sqm
  • Add 10% wastage = 0.06 sqm, total = 0.635
CodeInputUnitQuantityRate (INR)Amount (INR)
2704Aluminium Strip 40 mm wide and 2 mm thickMaterialkg3.98243.00967.14
8690High intensity retro - reflective sheetHigh intensity retro - reflective sheet as per IRC 67-2001Materialsqm0.981,345.001,318.10
Rate as per item no 10.2 of SH : Steel workRate as per item 10.2Sub-analysiskg29.76133.703,978.91
0128MateLabourday0.01816.008.16
0114BeldarLabourday0.25736.00184.00
9999Cost of material for drilling holes, nut bolts & rivets, facrication etcMaterialL.S.70.232.27159.42
Rate as per item no 13.61.1 of SH : FinishingRate as per item 13.61.1Sub-analysissqm1.09155.90169.93
Painting with epoxy paint on back side of aluminium sheet, Rate as per Item no. 13.52.1 of SH: FinishingRate as per item 13.52.1Sub-analysissqm0.635241.75153.51
9999Sundries & hole fast etc,MaterialL.S.31.22.2770.82
TOTAL
7,009.99
Add 1% Water charges on “W-A”
27.08
TOTAL
7,037.07
Add GST on “X-A” (multiplying factor 0.2127)
581.67
TOTAL
7,618.74
Add 15% CPOH on “Y-A”
497.46
TOTAL
8,116.20
Add Cess @1% on “Z-A’
38.14
Cost of 1 board
8,154.34
Cost for 1 each
8,154.34
Say
8,154.35

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1247. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.