CPWD Analysis of Rates · Road Work

Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x50 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:5 (1 cement : 5 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge

Item number
16.67
Analysis basis
Details of cost for 10 sqm
Priced inputs
8
Derived rate
1,600.55 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.67 Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x50 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:5 (1 cement : 5 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge — is derived from 8 priced inputs for 10 sqm and works out to ₹1,600.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • 20mm (bed and joints) CM. 1:5 (1 cement: 5
  • coarse sand)
CodeInputUnitQuantityRate (INR)Amount (INR)
8694Precast pavement slab 450 x 450 x 50 mm (M - 30)Materialeach48160.007,680.00
9977Carriage of slab.MaterialL.S.522.27118.04
Rate as per Item Number 3.10 of SH: MortarsRate as per item 3.10Sub-analysiscum0.253,850.75962.69
0155Mason (average)Labourday1.1857.00942.70
0100BandhaniLabourday1.1816.00897.60
0114BeldarLabourday0.55736.00404.80
0101BhistiLabourday0.27816.00220.32
9999SundriesMaterialL.S.10.792.2724.49
TOTAL
11,250.64
Add 1 % Water charges on “W”
112.51
TOTAL
11,363.15
Add GST on “X” (multiplying factor 0.2127)
2,416.94
TOTAL
13,780.09
Add 15% CPOH on “Y”
2,067.01
TOTAL
15,847.10
Add Cess @ 1% on “Z”
158.47
Cost for 10 sqm.
16,005.57
Cost for 1 sqm
1,600.56
Say
1,600.55

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1251. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works