Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x50 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:5 (1 cement : 5 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge

Item number
16.67
Analysis basis
10 sqm
Priced inputs
8
Derived rate
₹1,600.55/ SQM
D-01/RATE ANALYSISITEM 16.67

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.67 (Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x50 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:5 (1 cement : 5 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge) is derived from 8 priced inputs for 10 sqm and works out to ₹1,600.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 20mm (bed and joints) CM. 1:5 (1 cement: 5
  • coarse sand)
ANALYSIS OF RATES · ITEM 16.67DETAILS OF COST FOR 10 SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
8694MATPrecast pavement slab 450 x 450 x 50 mm (M - 30)each48160.007,680.00
9977MATCarriage of slab.L.S.522.27118.04
SUBRate as per Item Number 3.10 of SH: MortarsRate as per item 3.10cum0.253,850.75962.69
0155LABMason (average)day1.1857.00942.70
0100LABBandhaniday1.1816.00897.60
0114LABBeldarday0.55736.00404.80
0101LABBhistiday0.27816.00220.32
9999MATSundriesL.S.10.792.2724.49
BUILD-UP TO RATE
TOTAL
11,250.64
Add 1 % Water charges on “W”
+112.51
TOTAL
11,363.15
Add GST on “X” (multiplying factor 0.2127)
+2,416.94
TOTAL
13,780.09
Add 15% CPOH on “Y”
+2,067.01
TOTAL
15,847.10
Add Cess @ 1% on “Z”
+158.47
Cost for 10 sqm.
16,005.57
Cost for 1 sqm
1,600.56
SAY
₹1,600.55
D-02/SOURCEPRINTED PAGE 1251
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1251

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1251. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.