Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x50 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:5 (1 cement : 5 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge
- Item number
- 16.67
- Analysis basis
- 10 sqm
- Priced inputs
- 8
- Derived rate
- ₹1,600.55/ SQM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.67 (Providing and fixing at or near ground level factory made RCC pavement slab of M-30 grade of size 450x450x50 mm, including reinforcement with 6 mm dia M.S. bars 4 nos on each side, including setting in position in footpath to the required level and line over a bed of 20 mm average thick cement mortar 1:5 (1 cement : 5 coarse sand), having joint thickness not more than 5mm except on curve, including filling of joints with same cement mortar and making grooves etc. complete as per direction of Engineer-in-charge) is derived from 8 priced inputs for 10 sqm and works out to ₹1,600.55 per sqm after water charges, GST, CPOH and cess. The full build-up is below.
- 20mm (bed and joints) CM. 1:5 (1 cement: 5
- coarse sand)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 8694 | MAT | Precast pavement slab 450 x 450 x 50 mm (M - 30) | each | 48 | 160.00 | 7,680.00 |
| 9977 | MAT | Carriage of slab. | L.S. | 52 | 2.27 | 118.04 |
| SUB | Rate as per Item Number 3.10 of SH: MortarsRate as per item 3.10 | cum | 0.25 | 3,850.75 | 962.69 | |
| 0155 | LAB | Mason (average) | day | 1.1 | 857.00 | 942.70 |
| 0100 | LAB | Bandhani | day | 1.1 | 816.00 | 897.60 |
| 0114 | LAB | Beldar | day | 0.55 | 736.00 | 404.80 |
| 0101 | LAB | Bhisti | day | 0.27 | 816.00 | 220.32 |
| 9999 | MAT | Sundries | L.S. | 10.79 | 2.27 | 24.49 |
- TOTAL
- 11,250.64
- Add 1 % Water charges on “W”
- +112.51
- TOTAL
- 11,363.15
- Add GST on “X” (multiplying factor 0.2127)
- +2,416.94
- TOTAL
- 13,780.09
- Add 15% CPOH on “Y”
- +2,067.01
- TOTAL
- 15,847.10
- Add Cess @ 1% on “Z”
- +158.47
- Cost for 10 sqm.
- 16,005.57
- Cost for 1 sqm
- 1,600.56
- SAY
- ₹1,600.55
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1251
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1251. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate