CPWD Analysis of Rates · Road Work
Supplying, stacking and Spreading 6 mm thick red bajri, watering and rolling complete including preparation of the surface and rolling
With road roller/ hand roller
- Item number
- 16.6.1
- Analysis basis
- Details of cost for 6 mm thick and 100 sqm
- Priced inputs
- 5
- Derived rate
- ₹24.45 / mm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.6.1 — Supplying, stacking and Spreading 6 mm thick red bajri, watering and rolling complete including preparation of the surface and rolling With road roller/ hand roller — is derived from 5 priced inputs for 6 mm and works out to ₹24.45 per mm after water charges, GST, CPOH and cess. The full build-up is below.
- area
- (A) Supplying and stacking of Red bajri at
- site.
- (B) Spreading of red bajri
- Roller charges (one roller does 1860sqm.
- consolidation per day of 8 hours and uses
- 18 litres of diesel oil)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0304 | BajriMaterial | cum | 0.6 | 1,100.00 | 660.00 |
| 0114 | BeldarLabour | day | 0.54 | 736.00 | 397.44 |
| 0101 | BhistiLabour | day | 0.54 | 816.00 | 440.64 |
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonneMachinery | day | 0.054 | 3,350.00 | 180.90 |
| 0113 | ChowkidarLabour | day | 0.054 | 736.00 | 39.74 |
- TOTAL
- 1,718.72
- Add 1 % Water charges on “W”
- 17.19
- TOTAL
- 1,735.91
- Add GST on “X” (multiplying factor 0.2127)
- 369.23
- TOTAL
- 2,105.14
- Add 15% CPOH on “Y”
- 315.77
- TOTAL
- 2,420.91
- Add Cess @ 1% on “Z”
- 24.21
- Cost for 100 sqm.
- 2,445.12
- Cost per sqm.
- 24.45
- Say
- 24.45
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1151. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.