Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete. (payment for brick aggregate and moorum etc. to be made separately)

Over burnt (Jhama) brick aggregate 90 mm to 45 mm

Item number
16.5.2
Analysis basis
Details of cost for 1 cum.
Priced inputs
6
Derived rate
879.70 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.5.2 Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete. (payment for brick aggregate and moorum etc. to be made separately) Over burnt (Jhama) brick aggregate 90 mm to 45 mm — is derived from 6 priced inputs for 1 cum and works out to ₹879.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Roller charges (one roller does 230cum.
  • consolidation per day of 8 hours and uses
  • 18 litres of diesel oil)
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.35736.00257.60
0115CoolieLabourday0.26736.00191.36
0101BhistiLabourday0.18816.00146.88
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.0043,350.0013.40
0113ChowkidarLabourday0.004736.002.94
9999SundriesMaterialL.S.2.732.276.20
TOTAL
618.38
Add 1 % Water charges on “W”
6.18
TOTAL
624.56
Add GST on “X” (multiplying factor 0.2127)
132.84
TOTAL
757.40
Add 15% CPOH on “Y”
113.61
TOTAL
871.01
Add Cess @ 1% on “Z”
8.71
Cost for one cum.
879.72
Say
879.70

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1151. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.