Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete. (payment for brick aggregate and moorum etc. to be made separately)

Over burnt (Jhama) brick aggregate 90 mm to 45 mm
Item number
16.5.2
Analysis basis
1 cum
Priced inputs
6
Derived rate
₹879.70/ CUM
D-01/RATE ANALYSISITEM 16.5.2

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.5.2 (Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete. (payment for brick aggregate and moorum etc. to be made separately) Over burnt (Jhama) brick aggregate 90 mm to 45 mm) is derived from 6 priced inputs for 1 cum and works out to ₹879.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Roller charges (one roller does 230cum.
  • consolidation per day of 8 hours and uses
  • 18 litres of diesel oil)
ANALYSIS OF RATES · ITEM 16.5.2DETAILS OF COST FOR 1 CUM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0114LABBeldarday0.35736.00257.60
0115LABCoolieday0.26736.00191.36
0101LABBhistiday0.18816.00146.88
0003MACHHire charges of Diesel Road Roller - 8 to 10 tonneday0.0043,350.0013.40
0113LABChowkidarday0.004736.002.94
9999MATSundriesL.S.2.732.276.20
BUILD-UP TO RATE
TOTAL
618.38
Add 1 % Water charges on “W”
+6.18
TOTAL
624.56
Add GST on “X” (multiplying factor 0.2127)
+132.84
TOTAL
757.40
Add 15% CPOH on “Y”
+113.61
TOTAL
871.01
Add Cess @ 1% on “Z”
+8.71
Cost for one cum.
879.72
SAY
₹879.70
D-02/SOURCEPRINTED PAGE 1151
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1151

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1151. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.