Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete. (payment for brick aggregate and moorum etc. to be made separately)
- Item number
- 16.5.1
- Analysis basis
- 1 cum
- Priced inputs
- 6
- Derived rate
- ₹879.70/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.5.1 (Laying water bound macadam sub-base with brick aggregate and binding material, earth etc. including screening, sorting and spreading to template and consolidation with light power road-roller etc. complete. (payment for brick aggregate and moorum etc. to be made separately) Over burnt (Jhama) brick aggregate 120 mm to 40 mm) is derived from 6 priced inputs for 1 cum and works out to ₹879.70 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Roller charges (one roller does 230cum.
- consolidation per day of 8 hours and uses
- 18 litres of diesel oil)
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0114 | LAB | Beldar | day | 0.35 | 736.00 | 257.60 |
| 0115 | LAB | Coolie | day | 0.26 | 736.00 | 191.36 |
| 0101 | LAB | Bhisti | Day | 0.18 | 816.00 | 146.88 |
| 0003 | MACH | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.004 | 3,350.00 | 13.40 |
| 0113 | LAB | Chowkidar | day | 0.004 | 736.00 | 2.94 |
| 9999 | MAT | Sundries | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 618.38
- Add 1 % Water charges on “W”
- +6.18
- TOTAL
- 624.56
- Add GST on “X” (multiplying factor 0.2127)
- +132.84
- TOTAL
- 757.40
- Add 15% CPOH on “Y”
- +113.61
- TOTAL
- 871.01
- Add Cess @ 1% on “Z”
- +8.71
- Cost for one cum.
- 879.72
- SAY
- ₹879.70
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1150
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1150. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.