CPWD Analysis of Rates · Road Work
Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road/vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening / binding material to fill up interstices of coarse aggregate, watering and compacting to the required density
- Item number
- 16.4
- Analysis basis
- Details of cost for 1 cum
- Priced inputs
- 6
- Derived rate
- ₹1,046.95 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.4 — Laying, spreading and compacting stone aggregate of specified sizes to WBM specifications in uniform thickness, hand picking, rolling with 3 wheeled road/vibratory roller 8-10 tonne capacity in stages to proper grade and camber, applying and brooming requisite type of screening / binding material to fill up interstices of coarse aggregate, watering and compacting to the required density — is derived from 6 priced inputs for 1 cum and works out to ₹1,046.95 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Roller charges (one roller does 30 cum
- consolidation per day of 8 hours and uses
- 18 litres of diesel oil).
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0114 | BeldarLabour | day | 0.26 | 736.00 | 191.36 |
| 0115 | CoolieLabour | day | 0.26 | 736.00 | 191.36 |
| 0101 | BhistiLabour | day | 0.26 | 816.00 | 212.16 |
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonneMachinery | day | 0.033 | 3,350.00 | 110.55 |
| 0113 | ChowkidarLabour | day | 0.033 | 736.00 | 24.29 |
| 9999 | SundriesMaterial | L.S. | 2.73 | 2.27 | 6.20 |
- TOTAL
- 735.92
- Add 1 % Water charges on “W”
- 7.36
- TOTAL
- 743.28
- Add GST on “X” (multiplying factor 0.2127)
- 158.10
- TOTAL
- 901.38
- Add 15% CPOH on “Y”
- 135.21
- TOTAL
- 1,036.59
- Add Cess @ 1% on “Z”
- 10.37
- Cost for 1 cum
- 1,046.96
- Say
- 1,046.95
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1149. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.