CPWD Analysis of Rates · Road Work

Supplying and stacking at site

Moorum

Item number
16.3.10
Analysis basis
Details of cost for 1 cum.
Priced inputs
1
Derived rate
768.25 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.10 Supplying and stacking at site Moorum — is derived from 1 priced inputs for 1 cum and works out to ₹768.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.

CodeInputUnitQuantityRate (INR)Amount (INR)
0810MoorumMaterialcum1540.00540.00
TOTAL
540.00
Add 1 % Water charges on "W"
5.40
TOTAL
545.40
Add GST on "X" (multiplying factor 0.2127)
116.01
TOTAL
661.41
Add 15% CPOH on "Y"
99.21
TOTAL
760.62
Add Cess @ 1% on "Z"
7.61
Cost for one cum.
768.23
Say
768.25

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1149. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.