Supplying and stacking at site
- Item number
- 16.3.10
- Analysis basis
- 1 cum
- Priced inputs
- 1
- Derived rate
- ₹768.25/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.10 (Supplying and stacking at site Moorum) is derived from 1 priced inputs for 1 cum and works out to ₹768.25 per cum after water charges, GST, CPOH and cess. The full build-up is below.
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0810 | MAT | Moorum | cum | 1 | 540.00 | 540.00 |
- TOTAL
- 540.00
- Add 1 % Water charges on "W"
- +5.40
- TOTAL
- 545.40
- Add GST on "X" (multiplying factor 0.2127)
- +116.01
- TOTAL
- 661.41
- Add 15% CPOH on "Y"
- +99.21
- TOTAL
- 760.62
- Add Cess @ 1% on "Z"
- +7.61
- Cost for one cum.
- 768.23
- SAY
- ₹768.25
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1149
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1149. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.