Skip to main content

CPWD Analysis of Rates · Road Work

Supplying and stacking at site

Good earth

Item number
16.3.9
Analysis basis
Details of cost for 1 cum.
Priced inputs
4
Derived rate
775.50 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.3.9 Supplying and stacking at site Good earth — is derived from 4 priced inputs for 1 cum and works out to ₹775.50 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Excavation :
  • by mechanical transport upto 5 km lead
CodeInputUnitQuantityRate (INR)Amount (INR)
0114BeldarLabourday0.177736.00130.27
0115CoolieLabourday0.167736.00122.91
0979Royalty for good earthMaterialcum160.0060.00
2241Carriage of Good earthMaterialcum1231.93231.93
TOTAL
545.11
Add 1 % Water charges on “W”
5.45
TOTAL
550.56
Add GST on “X” (multiplying factor 0.2127)
117.10
TOTAL
667.66
Add 15% CPOH on “Y”
100.15
TOTAL
767.81
Add Cess @ 1% on “Z”
7.68
Cost per cum.
775.49
Say
775.50

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1149. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works