Sub Analysis X for sub analysis item Number 16.52Y
- Item number
- 16.52X
- Analysis basis
- 1cum of
- Priced inputs
- 7
- Derived rate
- ₹2,665.15/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.52X (Sub Analysis X for sub analysis item Number 16.52Y) is derived from 7 priced inputs for 1cum of and works out to ₹2,665.15 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Sub Analysis 16.52X for use in sub analysis
- of 16.52Y
- mortar 1:2:3 (lime:2 flyash:3 coarse sand).
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0773 | MAT | Unslaked lime | quintal | 1.52 | 325.00 | 494.00 |
| 1980 | MAT | FlyashFly ash | cum | 0.48 | 12.00 | 5.76 |
| 0982 | MAT | Coarse sand (zone III) | cum | 0.72 | 1,450.00 | 1,044.00 |
| 0114 | LAB | Beldar | day | 0.9 | 736.00 | 662.40 |
| 0101 | LAB | Bhisti | day | 0.45 | 816.00 | 367.20 |
| 9999 | MAT | Running and upkeep of mortar mill | L.S. | 26.91 | 2.27 | 61.09 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
- TOTAL
- 2,665.14
- Cost of 1.00 cum
- 2,665.14
- SAY
- ₹2,665.15
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1218
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1218. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.