- ₹3,744.60/ CUM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.52Y (Sub Analysis Y for Item Number 16.52) is derived from 12 priced inputs for 1 cum and works out to ₹3,744.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Sub Analysis ‘Y’ (16.52Y) for use in Item No.
- 16.52
- concrete
- Lime Flyash mortar
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| SUB | Rate as per sub analysis of Item No 16.52XRate as per item 16.52X | cum | 0.4 | 2,665.15 | 1,066.06 | |
| 0295 | MAT | Stone Aggregate (Single size) : 20 mm nominal size | cum | 0.64 | 1,425.00 | 912.00 |
| 0297 | MAT | Stone Aggregate (Single size) : 10 mm nominal size | cum | 0.21 | 1,400.00 | 294.00 |
| 0114 | LAB | Beldar | day | 0.65 | 736.00 | 478.40 |
| 0115 | LAB | Coolie | day | 0.6 | 736.00 | 441.60 |
| 0101 | LAB | Bhisti | day | 0.27 | 816.00 | 220.32 |
| 0123 | LAB | Mason 1st classMason 1st class | day | 0.05 | 897.00 | 44.85 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 0.05 | 816.00 | 40.80 |
| 0128 | LAB | Mate | day | 0.04 | 816.00 | 32.64 |
| 9999 | MAT | Hire and running charges of mixer | L.S. | 26.91 | 2.27 | 61.09 |
| 9999 | MAT | Sundries | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | MAT | Hire charges of steel moulds, table vibrators, rammers, bolts, nuts and washers etc | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 3,744.62
- Cost of 1.00 cum
- 3,744.62
- SAY
- ₹3,744.60
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1219
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1219. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.