CPWD Analysis of Rates · Road Work
Sub Analysis Y for Item Number 16.52
- Item number
- 16.52Y
- Analysis basis
- Details of cost for 1 cum. of cement
- Priced inputs
- 12
- Derived rate
- ₹3,744.60 / cum
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.52Y — Sub Analysis Y for Item Number 16.52 — is derived from 12 priced inputs for 1 cum and works out to ₹3,744.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.
- Sub Analysis ‘Y’ (16.52Y) for use in Item No.
- 16.52
- concrete
- Lime Flyash mortar
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| Rate as per sub analysis of Item No 16.52XRate as per item 16.52XSub-analysis | cum | 0.4 | 2,665.15 | 1,066.06 | |
| 0295 | Stone Aggregate (Single size) : 20 mm nominal sizeMaterial | cum | 0.64 | 1,425.00 | 912.00 |
| 0297 | Stone Aggregate (Single size) : 10 mm nominal sizeMaterial | cum | 0.21 | 1,400.00 | 294.00 |
| 0114 | BeldarLabour | day | 0.65 | 736.00 | 478.40 |
| 0115 | CoolieLabour | day | 0.6 | 736.00 | 441.60 |
| 0101 | BhistiLabour | day | 0.27 | 816.00 | 220.32 |
| 0123 | Mason 1st classMason 1st classLabour | day | 0.05 | 897.00 | 44.85 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 0.05 | 816.00 | 40.80 |
| 0128 | MateLabour | day | 0.04 | 816.00 | 32.64 |
| 9999 | Hire and running charges of mixerMaterial | L.S. | 26.91 | 2.27 | 61.09 |
| 9999 | SundriesMaterial | L.S. | 13.52 | 2.27 | 30.69 |
| 9999 | Hire charges of steel moulds, table vibrators, rammers, bolts, nuts and washers etcMaterial | L.S. | 53.82 | 2.27 | 122.17 |
- TOTAL
- 3,744.62
- Cost of 1.00 cum
- 3,744.62
- Say
- 3,744.60
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1219. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works