D-01/RATE ANALYSISITEM 16.52Y

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.52Y (Sub Analysis Y for Item Number 16.52) is derived from 12 priced inputs for 1 cum and works out to ₹3,744.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • Sub Analysis ‘Y’ (16.52Y) for use in Item No.
  • 16.52
  • concrete
  • Lime Flyash mortar
ANALYSIS OF RATES · ITEM 16.52YDETAILS OF COST FOR 1 CUM. OF CEMENT
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUBRate as per sub analysis of Item No 16.52XRate as per item 16.52Xcum0.42,665.151,066.06
0295MATStone Aggregate (Single size) : 20 mm nominal sizecum0.641,425.00912.00
0297MATStone Aggregate (Single size) : 10 mm nominal sizecum0.211,400.00294.00
0114LABBeldarday0.65736.00478.40
0115LABCoolieday0.6736.00441.60
0101LABBhistiday0.27816.00220.32
0123LABMason 1st classMason 1st classday0.05897.0044.85
0124LABMason 2nd classMason 2nd classday0.05816.0040.80
0128LABMateday0.04816.0032.64
9999MATHire and running charges of mixerL.S.26.912.2761.09
9999MATSundriesL.S.13.522.2730.69
9999MATHire charges of steel moulds, table vibrators, rammers, bolts, nuts and washers etcL.S.53.822.27122.17
BUILD-UP TO RATE
TOTAL
3,744.62
Cost of 1.00 cum
3,744.62
SAY
₹3,744.60
D-02/SOURCEPRINTED PAGE 1219
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1219

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1219. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.