CPWD Analysis of Rates · Road Work

Sub Analysis Y for Item Number 16.52

Item number
16.52Y
Analysis basis
Details of cost for 1 cum. of cement
Priced inputs
12
Derived rate
3,744.60 / cum

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.52Y Sub Analysis Y for Item Number 16.52 — is derived from 12 priced inputs for 1 cum and works out to ₹3,744.60 per cum after water charges, GST, CPOH and cess. The full build-up is below.

  • Sub Analysis ‘Y’ (16.52Y) for use in Item No.
  • 16.52
  • concrete
  • Lime Flyash mortar
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per sub analysis of Item No 16.52XRate as per item 16.52XSub-analysiscum0.42,665.151,066.06
0295Stone Aggregate (Single size) : 20 mm nominal sizeMaterialcum0.641,425.00912.00
0297Stone Aggregate (Single size) : 10 mm nominal sizeMaterialcum0.211,400.00294.00
0114BeldarLabourday0.65736.00478.40
0115CoolieLabourday0.6736.00441.60
0101BhistiLabourday0.27816.00220.32
0123Mason 1st classMason 1st classLabourday0.05897.0044.85
0124Mason 2nd classMason 2nd classLabourday0.05816.0040.80
0128MateLabourday0.04816.0032.64
9999Hire and running charges of mixerMaterialL.S.26.912.2761.09
9999SundriesMaterialL.S.13.522.2730.69
9999Hire charges of steel moulds, table vibrators, rammers, bolts, nuts and washers etcMaterialL.S.53.822.27122.17
TOTAL
3,744.62
Cost of 1.00 cum
3,744.62
Say
3,744.60

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1219. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.

See how estimation works