Providing and fixing precast lime fly ash concrete blocks 1:2:3:6 (1 lime: 2 fly ash: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size), including finishing with 10mm thick cement mortar 1:3 (1 cement : 3 coarse sand) in foot paths, including preparation of sub grade with a hand rammer, laying 10 mm thick leveling course of fine sand (jamuna sand) and filling the joints with fine sand

Item number
16.52
Analysis basis
Details of cost for a path of area
Priced inputs
16
Derived rate
13,719.05 / a path

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.52 Providing and fixing precast lime fly ash concrete blocks 1:2:3:6 (1 lime: 2 fly ash: 3 coarse sand : 6 graded stone aggregate 20 mm nominal size), including finishing with 10mm thick cement mortar 1:3 (1 cement : 3 coarse sand) in foot paths, including preparation of sub grade with a hand rammer, laying 10 mm thick leveling course of fine sand (jamuna sand) and filling the joints with fine sand — is derived from 16 priced inputs for a path and works out to ₹13,719.05 per a path after water charges, GST, CPOH and cess. The full build-up is below.

  • 100sqm/9cum.
  • No. of blocks required for 100sqm. = 1080
  • nos.
  • (a) Concrete in blocks
  • (1080x0.30x0.30x0.09 = 8.75 cum.)
  • (b) Labour for surface excavation :
  • (c) For levelling course of fine sand
  • (d) For finishing with 10mm thick cement
  • plaster
  • cement plaster with cement mortar 1:3(1
  • Cement: 3 Coarse sand)
  • qty. for 97.2sqm. = 0.972 cum
  • (e) For laying blocks and filling joints with
  • Jamuna sand for filling joints 5mm (av.) thick
CodeInputUnitQuantityRate (INR)Amount (INR)
Rate as per sub analysis Item Number 16.52Y of SH:Road WorkRate as per item 16.52YSub-analysiscum8.753,744.6032,765.25
0114BeldarLabourday7.2736.005,299.20
0115CoolieLabourday6736.004,416.00
6501Sand zone V (Jamuna)Materialcum11,320.001,320.00
0114BeldarLabourday0.089736.0065.50
0115CoolieLabourday0.107736.0078.75
0101BhistiLabourday0.035816.0028.56
Rate as per Item Number 3.8 of SH: MortarsRate as per item 3.8Sub-analysiscum0.9724,881.954,745.26
0155Mason (average)Labourday7.87857.006,744.59
0115CoolieLabourday7.87736.005,792.32
0101BhistiLabourday2.62816.002,137.92
9999Scaffolding and sundriesMaterialL.S.122.22.27277.39
6501Sand zone V (Jamuna)Materialcum0.051,320.0066.00
0123Mason 1st classMason 1st classLabourday9897.008,073.00
0115CoolieLabourday19.8736.0014,572.80
0101BhistiLabourday0.5816.00408.00
TOTAL
86,790.54
Add 1 % Water charges on “W”
867.91
TOTAL
87,658.45
Add GST on “X” (multiplying factor 0.2127)
18,644.95
TOTAL
1,06,303.40
Add 15% CPOH on “Y”
15,945.51
TOTAL
1,22,248.91
Add Cess @ 1% on “Z”
1,222.49
Cost for 9 cum.
1,23,471.40
Rate per cum.
13,719.04
Say
13,719.05

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1217. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.