CPWD Analysis of Rates · Road Work

Preparation of sub-base road pavement with commercial dry lime (slaked), fly ash stabilised soil with a mix of 3% lime, 12% fly ash and 85% local suitable soil by weight, so as to achieve minimum field C.B.R. of 20, including mixing, rolling with road roller curing etc. all complete

Minimum thickness 15 cm

Item number
16.51.1
Analysis basis
Details of cost for 66.7 sqm. or 10 cum.
Priced inputs
14
Derived rate
1,514.40 / sqm

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.51.1 Preparation of sub-base road pavement with commercial dry lime (slaked), fly ash stabilised soil with a mix of 3% lime, 12% fly ash and 85% local suitable soil by weight, so as to achieve minimum field C.B.R. of 20, including mixing, rolling with road roller curing etc. all complete Minimum thickness 15 cm — is derived from 14 priced inputs for 66.7 sqm and works out to ₹1,514.40 per sqm after water charges, GST, CPOH and cess. The full build-up is below.

  • (ii) For mixing :
  • (iii) For rolling layers :
  • (iv) Labour for spreading and watering :
CodeInputUnitQuantityRate (INR)Amount (INR)
0777Dry hydrated lime (factory made)Materialquintal4.1315.001,291.50
1980FlyashFly ashMaterialcum2.7712.0033.24
0114BeldarLabourday1.16736.00853.76
0115CoolieLabourday1.16736.00853.76
0979Royalty for good earthMaterialcum6.5560.00393.00
2241Carriage of Good earthMaterialcum6.55231.931,519.14
0114BeldarLabourday0.25736.00184.00
0115CoolieLabourday0.25736.00184.00
0113ChowkidarLabourday0.008736.005.89
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.0083,350.0026.80
9999SundriesMaterialL.S.1.82.274.09
0114BeldarLabourday2.6736.001,913.60
0115CoolieLabourday2.6736.001,913.60
0101BhistiLabourday1.8816.001,468.80
TOTAL
10,645.18
Add 1 % Water charges on “W”
106.45
TOTAL
10,751.63
Add GST on “X” (multiplying factor 0.2127)
2,286.87
TOTAL
13,038.50
Add 15% CPOH on “Y”
1,955.78
TOTAL
14,994.28
Add Cess @ 1% on “Z”
149.94
Cost for 10 cum.
15,144.22
Cost for 1 cum.
1,514.42
Say
1,514.40

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1217. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.