CPWD Analysis of Rates · Road Work
Making bell mouth opening/ entrance of size 100x50x50 cm for drainage pipe under footpath, including providing cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) for shape of bell mouth, including plastering providing and fixing precast R.C.C./ S.F.R.C. slab including plastering with cement mortar 1:3 (1 cement : 3 fine sand) of 6 mm thickness on exposed surface of the slab & bell mouth including centring, shuttering & neat cement punning inside the bell mouth etc. all complete
- Item number
- 16.49
- Analysis basis
- Details of cost for 10 Nos.
- Priced inputs
- 19
- Derived rate
- ₹3,050.40 / Nos
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.49 — Making bell mouth opening/ entrance of size 100x50x50 cm for drainage pipe under footpath, including providing cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) for shape of bell mouth, including plastering providing and fixing precast R.C.C./ S.F.R.C. slab including plastering with cement mortar 1:3 (1 cement : 3 fine sand) of 6 mm thickness on exposed surface of the slab & bell mouth including centring, shuttering & neat cement punning inside the bell mouth etc. all complete — is derived from 19 priced inputs for 10 Nos and works out to ₹3,050.40 each after water charges, GST, CPOH and cess. The full build-up is below.
- (i) Earth work in excavation
- Channel :- 10x1x1.00x0.20x0.15 =
- 0.30+ Bell mouth :-10x1x1.00x0.50x
- (0.18+0.075)/2 = 0.64 Total = 0.94
- (ii) Cement concrete 1:4:8
- Channel :-10x1x1.00x0.20x0.075 = 0.15
- cum
- (iii) Cement concrete 1:3:6
- Channel 10x1x1.00x0.20x0.075 = 0.15 +
- Bed of bell mouth :
- 10x1x1.00x0.50x(0.18+0.075)/2 = 0.64 +
- Haunches portion
- 10x2x(0.35+0.075)/2x0.25x 0.375 = 0.40 +
- Rect part :10x2x0.35x0.25x0.375 = 0.65 +
- Quadrant portion :10x1[(0.3
- 0x0.30)-3.142/4(0.30)²]x 0.30 =0.06+
- Central middle part :10x1x0.30x0.25x0.075
- = 0.05
- Total = 1.95 cum.
- (iv) RCC in shelves
- 10x1x1.00x0.50x0.05 = 0.25cum.
- (v) Reinforcement for RCC @100kg/cum.
- 0.25x100=25kg.
- (vi) Centering and shuttering
- For shelves (sides)
- 10x2(1.00+0.50)x0.05 = 1.50+
- Front side of bell mouth :
- 10x2(0.446)x0.375 = 3.34 +
- Pipe portion:
- 10x[0.30x0.375-3.142/4(030)²] = 0.04 (x) +
- Out side of bell mouth
- 10x(1.00 =0.50)x0.45 = 9.00+
- 10x0.785x0.30x0.30 = (-)0.71
- Total = 13.17
- (vii) cement plaster on RCC slab
- 10x1.00x0.50 = 5.00 + 10x2(1.00+0.50)
- x0.05 = 1.50+ Total = 6.50 sqm.
- (viii) Neat cement punning:
- Qty. same as marked (x) at (9vi) = Total
- =3.34+0.04 = 3.38 sqm
- Channel portion:
- 10x1x(0.85+0.30)/2x0.25 = 1.43 Total = 4.81
- Labour for plaster
- Deduct pipe opening
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| (Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1Sub-analysis | cum | 0.94 | 260.30 | 244.68 | |
| Rate as per item no 4.1.8 of SH : Concrete WorkRate as per item 4.1.8Sub-analysis | cum | 0.15 | 6,812.00 | 1,021.80 | |
| (Rate as per item no.4.1.5 S.H. : Cement Concrete)Rate as per item 4.1.5Sub-analysis | cum | 1.95 | 7,294.70 | 14,224.67 | |
| Rate as per item no. 5.3 SH : RCCRate as per item 5.3Sub-analysis | cum | 0.25 | 11,505.50 | 2,876.38 | |
| Rate as per item no. 5.22.1 SH : RCCRate as per item 5.22.1Sub-analysis | kg | 25 | 107.10 | 2,677.50 | |
| Rate as per item No.5.9.1 of SH : RCRate as per item 5.9.1Sub-analysis | sqm | 13.17 | 392.15 | 5,164.62 | |
| Rate as per item No.5.23Rate as per item 5.23Sub-analysis | sqm | 6.5 | 300.45 | 1,952.93 | |
| Rate as per item no.13.18 S.H. FinishingRate as per item 13.18Sub-analysis | sqm | 4.81 | 79.95 | 384.56 | |
| 0367 | Portland Cement (OPC-43 grade)Material | tonne | 0.024 | 5,156.00 | 123.74 |
| 0983 | Fine Sand (Zone IV)Material | cum | 0.05 | 980.00 | 49.00 |
| 0114 | BeldarLabour | day | 0.035 | 736.00 | 25.76 |
| 0101 | BhistiLabour | day | 0.003 | 816.00 | 2.45 |
| 9999 | Hire charges of mixerMaterial | L.S. | 1.27 | 2.27 | 2.88 |
| 9999 | SundriesMaterial | L.S. | 1.27 | 2.27 | 2.88 |
| 0155 | Mason (average)Labour | day | 0.33 | 857.00 | 282.81 |
| 0115 | CoolieLabour | day | 0.488 | 736.00 | 359.17 |
| 0101 | BhistiLabour | day | 0.6 | 816.00 | 489.60 |
| 9999 | Extra for removing burrMaterial | L.S. | 8.71 | 2.27 | 19.77 |
| 9999 | ScaffoldingMaterial | L.S. | 7.62 | 2.27 | 17.30 |
- TOTAL
- 29,922.50
- Add 1% Water charges on “W-A”
- 13.75
- TOTAL
- 29,936.25
- Add GST on “X-A” (multiplying factor 0.2127)
- 295.46
- TOTAL
- 30,231.71
- Add 15% CPOH on “Y-A”
- 252.69
- TOTAL
- 30,484.40
- Add Cess @1% on “Z-A’
- 19.37
- Cost of each
- 30,503.77
- Cost for 1 no.
- 3,050.38
- Say
- 3,050.40
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1214. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.