Making bell mouth opening/ entrance of size 100x50x50 cm for drainage pipe under footpath, including providing cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) for shape of bell mouth, including plastering providing and fixing precast R.C.C./ S.F.R.C. slab including plastering with cement mortar 1:3 (1 cement : 3 fine sand) of 6 mm thickness on exposed surface of the slab & bell mouth including centring, shuttering & neat cement punning inside the bell mouth etc. all complete

Item number
16.49
Analysis basis
10 Nos
Priced inputs
19
Derived rate
₹3,050.40/ NOS
D-01/RATE ANALYSISITEM 16.49

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.49 (Making bell mouth opening/ entrance of size 100x50x50 cm for drainage pipe under footpath, including providing cement concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size) for shape of bell mouth, including plastering providing and fixing precast R.C.C./ S.F.R.C. slab including plastering with cement mortar 1:3 (1 cement : 3 fine sand) of 6 mm thickness on exposed surface of the slab & bell mouth including centring, shuttering & neat cement punning inside the bell mouth etc. all complete) is derived from 19 priced inputs for 10 Nos and works out to ₹3,050.40 each after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • (i) Earth work in excavation
  • Channel :- 10x1x1.00x0.20x0.15 =
  • 0.30+ Bell mouth :-10x1x1.00x0.50x
  • (0.18+0.075)/2 = 0.64 Total = 0.94
  • (ii) Cement concrete 1:4:8
  • Channel :-10x1x1.00x0.20x0.075 = 0.15
  • cum
  • (iii) Cement concrete 1:3:6
  • Channel 10x1x1.00x0.20x0.075 = 0.15 +
  • Bed of bell mouth :
  • 10x1x1.00x0.50x(0.18+0.075)/2 = 0.64 +
  • Haunches portion
  • 10x2x(0.35+0.075)/2x0.25x 0.375 = 0.40 +
  • Rect part :10x2x0.35x0.25x0.375 = 0.65 +
  • Quadrant portion :10x1[(0.3
  • 0x0.30)-3.142/4(0.30)²]x 0.30 =0.06+
  • Central middle part :10x1x0.30x0.25x0.075
  • = 0.05
  • Total = 1.95 cum.
  • (iv) RCC in shelves
  • 10x1x1.00x0.50x0.05 = 0.25cum.
  • (v) Reinforcement for RCC @100kg/cum.
  • 0.25x100=25kg.
  • (vi) Centering and shuttering
  • For shelves (sides)
  • 10x2(1.00+0.50)x0.05 = 1.50+
  • Front side of bell mouth :
  • 10x2(0.446)x0.375 = 3.34 +
  • Pipe portion:
  • 10x[0.30x0.375-3.142/4(030)²] = 0.04 (x) +
  • Out side of bell mouth
  • 10x(1.00 =0.50)x0.45 = 9.00+
  • 10x0.785x0.30x0.30 = (-)0.71
  • Total = 13.17
  • (vii) cement plaster on RCC slab
  • 10x1.00x0.50 = 5.00 + 10x2(1.00+0.50)
  • x0.05 = 1.50+ Total = 6.50 sqm.
  • (viii) Neat cement punning:
  • Qty. same as marked (x) at (9vi) = Total
  • =3.34+0.04 = 3.38 sqm
  • Channel portion:
  • 10x1x(0.85+0.30)/2x0.25 = 1.43 Total = 4.81
  • Labour for plaster
  • Deduct pipe opening
ANALYSIS OF RATES · ITEM 16.49DETAILS OF COST FOR 10 NOS
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
SUB(Rate as per item no. 2.8.1 of SH: Earth work)Rate as per item 2.8.1cum0.94260.30244.68
SUBRate as per item no 4.1.8 of SH : Concrete WorkRate as per item 4.1.8cum0.156,812.001,021.80
SUB(Rate as per item no.4.1.5 S.H. : Cement Concrete)Rate as per item 4.1.5cum1.957,294.7014,224.67
SUBRate as per item no. 5.3 SH : RCCRate as per item 5.3cum0.2511,505.502,876.38
SUBRate as per item no. 5.22.1 SH : RCCRate as per item 5.22.1kg25107.102,677.50
SUBRate as per item No.5.9.1 of SH : RCRate as per item 5.9.1sqm13.17392.155,164.62
SUBRate as per item No.5.23Rate as per item 5.23sqm6.5300.451,952.93
SUBRate as per item no.13.18 S.H. FinishingRate as per item 13.18sqm4.8179.95384.56
0367MATPortland Cement (OPC-43 grade)tonne0.0245,156.00123.74
0983MATFine Sand (Zone IV)cum0.05980.0049.00
0114LABBeldarday0.035736.0025.76
0101LABBhistiday0.003816.002.45
9999MATHire charges of mixerL.S.1.272.272.88
9999MATSundriesL.S.1.272.272.88
0155LABMason (average)day0.33857.00282.81
0115LABCoolieday0.488736.00359.17
0101LABBhistiday0.6816.00489.60
9999MATExtra for removing burrL.S.8.712.2719.77
9999MATScaffoldingL.S.7.622.2717.30
BUILD-UP TO RATE
TOTAL
29,922.50
Add 1% Water charges on “W-A”
+13.75
TOTAL
29,936.25
Add GST on “X-A” (multiplying factor 0.2127)
+295.46
TOTAL
30,231.71
Add 15% CPOH on “Y-A”
+252.69
TOTAL
30,484.40
Add Cess @1% on “Z-A’
+19.37
Cost of each
30,503.77
Cost for 1 no.
3,050.38
SAY
₹3,050.40
D-02/SOURCEPRINTED PAGE 1214
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1214

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1214. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.