CPWD Analysis of Rates · Road Work
Painting road surface marking with adequate nos of coats to give uniform finish with ready mixed road marking paint conforming to IS : 164, on bituminous surface in white/yellow shade, including cleaning the surface of all dirt, scales, oil, grease and foreign material etc. complete
Old work (One or more coats)
- Item number
- 16.48.2
- Analysis basis
- Details of cost for 10sqm.
- Priced inputs
- 6
- Derived rate
- ₹189.85
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.48.2 — Painting road surface marking with adequate nos of coats to give uniform finish with ready mixed road marking paint conforming to IS : 164, on bituminous surface in white/yellow shade, including cleaning the surface of all dirt, scales, oil, grease and foreign material etc. complete Old work (One or more coats) — is derived from 6 priced inputs and works out to ₹189.85 after water charges, GST, CPOH and cess. The full build-up is below.
- (conforming to IS 164 spirit base)
- (stretching of rope & errecting of barricading
- etc.)
- (including painting brush, wire brush, labour
- for controlling traffic and other T&P etc.)
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 7255 | Road marking paint (spirit based)Material | litre | 0.89 | 124.00 | 110.36 |
| 9977 | Carriage of paint.Material | L.S. | 0.65 | 2.27 | 1.48 |
| 0128 | MateLabour | day | 0.06 | 816.00 | 48.96 |
| 0131 | PainterLabour | day | 0.36 | 816.00 | 293.76 |
| 0114 | BeldarLabour | day | 1.12 | 736.00 | 824.32 |
| 9999 | SundriesMaterial | L.S. | 24.44 | 2.27 | 55.48 |
- TOTAL
- 1,334.36
- Add 1 % Water charges on “W”
- 13.34
- TOTAL
- 1,347.70
- Add GST on “X” (multiplying factor 0.2127)
- 286.66
- TOTAL
- 1,634.36
- Add 15% CPOH on “Y”
- 245.15
- TOTAL
- 1,879.51
- Add Cess @ 1% on “Z”
- 18.80
- Cost for 10 sqm.
- 1,898.31
- Cost per sqm.
- 189.83
- Say
- 189.85
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1213. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.