Painting runway/taxi track/apron marking with adequate nos of coats to give uniform finish with road marking paint of superior make as approved by the Engineer-in-charge, i/c cleaning the surface of ail dirt, scales, oil, grease and other foreign material etc. and lining out complete

New work (Two or more coats)
Item number
16.47.1
Analysis basis
Details of cost for 10sqm.
Priced inputs
5
Derived rate
₹188.20
D-01/RATE ANALYSISITEM 16.47.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.47.1 (Painting runway/taxi track/apron marking with adequate nos of coats to give uniform finish with road marking paint of superior make as approved by the Engineer-in-charge, i/c cleaning the surface of ail dirt, scales, oil, grease and other foreign material etc. and lining out complete New work (Two or more coats)) is derived from 5 priced inputs and works out to ₹188.20 after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • 1st Coat - 1.66 +
  • 2nd Coat -1.13
  • Total = 2.79
  • (including painting brush, wire brush, labour
  • for controlling traffic and other T&P etc.)
ANALYSIS OF RATES · ITEM 16.47.1DETAILS OF COST FOR 10SQM
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
7256MATSuperior quality road marking paint (water based)litre2.79140.00390.60
9977MATCarriage of paintL.S.5.072.2711.51
0131LABPainterday0.54816.00440.64
0114LABBeldarday0.54736.00397.44
9999MATSundriesL.S.36.42.2782.63
BUILD-UP TO RATE
TOTAL
1,322.82
Add 1 % Water charges on “W”
+13.23
TOTAL
1,336.05
Add GST on “X” (multiplying factor 0.2127)
+284.18
TOTAL
1,620.23
Add 15% CPOH on “Y”
+243.03
TOTAL
1,863.26
Add Cess @ 1% on “Z”
+18.63
Cost for 10 sqm.
1,881.89
Cost per sqm.
188.19
SAY
₹188.20
D-02/SOURCEPRINTED PAGE 1212
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1212

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1212. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.

D-03/ADJACENT ITEMSROAD WORK
ARCHED / ESTIMATING

Use this rate in a live estimate

This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.