Providing and filling in position rubberized bitumen hot sealing compound for sealing of expansion joints in roads / pavements all complete as per direction of the Engineer-in-Charge
- Item number
- 16.46.1
- Analysis basis
- 12 mm
- Priced inputs
- 4
- Derived rate
- ₹8.65/ MM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.46.1 (Providing and filling in position rubberized bitumen hot sealing compound for sealing of expansion joints in roads / pavements all complete as per direction of the Engineer-in-Charge Using grade ‘A’ sealing compound conforming to IS: 1834) is derived from 4 priced inputs for 12 mm and works out to ₹8.65 per mm after water charges, GST, CPOH and cess. The full build-up is below.
- and 300 metres in length.
- Sealing compound300x0.012x0.025 = 0.09cum.
- Weight 1020 kg. per cum. = 1020x0.09 =
- 91.80 kg
- 91.8 kg = 0.0918 Say 0.092 tonne
- Labour for filling :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0314 | MAT | Bitumen hot sealing compound : grade A | kilogram | 91.8 | 30.00 | 2,754.00 |
| 0124 | LAB | Mason 2nd classMason 2nd class | day | 1 | 816.00 | 816.00 |
| 0114 | LAB | Beldar | day | 2.5 | 736.00 | 1,840.00 |
| 9999 | MAT | Sundries | L.S. | 20.67 | 2.27 | 46.92 |
- TOTAL
- 5,456.92
- Add 1 % Water charges on “W”
- +54.57
- TOTAL
- 5,511.49
- Add GST on “X” (multiplying factor 0.2127)
- +1,172.29
- TOTAL
- 6,683.78
- Add 15% CPOH on “Y”
- +1,002.57
- TOTAL
- 7,686.35
- Add Cess @ 1% on “Z”
- +76.86
- Cost for 12 mm depth, 25 mm width and 300m length
- 7,763.21
- Cost for one cm. depth one cm. width per metre length.
- 8.63
- SAY
- ₹8.65
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1211
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1211. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. We can do this for you: send the tender and we return a priced BOQ on the applicable schedule, with rate build-ups and an engineer's sign-off.