CPWD Analysis of Rates · Road Work
Providing and filling in position rubberized bitumen hot sealing compound for sealing of expansion joints in roads / pavements all complete as per direction of the Engineer-in-Charge
Using grade ‘A’ sealing compound conforming to IS: 1834
- Item number
- 16.46.1
- Analysis basis
- Details of cost for 12 mm wide 25 mm deep
- Priced inputs
- 4
- Derived rate
- ₹8.65 / mm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.46.1 — Providing and filling in position rubberized bitumen hot sealing compound for sealing of expansion joints in roads / pavements all complete as per direction of the Engineer-in-Charge Using grade ‘A’ sealing compound conforming to IS: 1834 — is derived from 4 priced inputs for 12 mm and works out to ₹8.65 per mm after water charges, GST, CPOH and cess. The full build-up is below.
- and 300 metres in length.
- Sealing compound300x0.012x0.025 = 0.09cum.
- Weight 1020 kg. per cum. = 1020x0.09 =
- 91.80 kg
- 91.8 kg = 0.0918 Say 0.092 tonne
- Labour for filling :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0314 | Bitumen hot sealing compound : grade AMaterial | kilogram | 91.8 | 30.00 | 2,754.00 |
| 0124 | Mason 2nd classMason 2nd classLabour | day | 1 | 816.00 | 816.00 |
| 0114 | BeldarLabour | day | 2.5 | 736.00 | 1,840.00 |
| 9999 | SundriesMaterial | L.S. | 20.67 | 2.27 | 46.92 |
- TOTAL
- 5,456.92
- Add 1 % Water charges on “W”
- 54.57
- TOTAL
- 5,511.49
- Add GST on “X” (multiplying factor 0.2127)
- 1,172.29
- TOTAL
- 6,683.78
- Add 15% CPOH on “Y”
- 1,002.57
- TOTAL
- 7,686.35
- Add Cess @ 1% on “Z”
- 76.86
- Cost for 12 mm depth, 25 mm width and 300m length
- 7,763.21
- Cost for one cm. depth one cm. width per metre length.
- 8.63
- Say
- 8.65
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1211. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.