R/DAR 2023

Providing and filling in position rubberized bitumen hot sealing compound for sealing of expansion joints in roads / pavements all complete as per direction of the Engineer-in-Charge

Using grade ‘A’ sealing compound conforming to IS: 1834
Item number
16.46.1
Analysis basis
12 mm
Priced inputs
4
Derived rate
₹8.65/ MM
D-01/RATE ANALYSISITEM 16.46.1

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.46.1 (Providing and filling in position rubberized bitumen hot sealing compound for sealing of expansion joints in roads / pavements all complete as per direction of the Engineer-in-Charge Using grade ‘A’ sealing compound conforming to IS: 1834) is derived from 4 priced inputs for 12 mm and works out to ₹8.65 per mm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • and 300 metres in length.
  • Sealing compound300x0.012x0.025 = 0.09cum.
  • Weight 1020 kg. per cum. = 1020x0.09 =
  • 91.80 kg
  • 91.8 kg = 0.0918 Say 0.092 tonne
  • Labour for filling :
ANALYSIS OF RATES · ITEM 16.46.1DETAILS OF COST FOR 12 MM WIDE 25 MM DEEP
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0314MATBitumen hot sealing compound : grade Akilogram91.830.002,754.00
0124LABMason 2nd classMason 2nd classday1816.00816.00
0114LABBeldarday2.5736.001,840.00
9999MATSundriesL.S.20.672.2746.92
BUILD-UP TO RATE
TOTAL
5,456.92
Add 1 % Water charges on “W”
+54.57
TOTAL
5,511.49
Add GST on “X” (multiplying factor 0.2127)
+1,172.29
TOTAL
6,683.78
Add 15% CPOH on “Y”
+1,002.57
TOTAL
7,686.35
Add Cess @ 1% on “Z”
+76.86
Cost for 12 mm depth, 25 mm width and 300m length
7,763.21
Cost for one cm. depth one cm. width per metre length.
8.63
SAY
₹8.65
D-02/SOURCEPRINTED PAGE 1211
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1211

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1211. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.