CPWD Analysis of Rates · Road Work
Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)
- Item number
- 16.45
- Analysis basis
- Details of cost for 12 mm thick 15cm deep
- Priced inputs
- 4
- Derived rate
- ₹5.30 / mm
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.45 — Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.) — is derived from 4 priced inputs for 12 mm and works out to ₹5.30 per mm after water charges, GST, CPOH and cess. The full build-up is below.
- and 300m in length
- Labour for cutting the board in strips,
- making the joints clean and dust free and
- fixing etc. :
| Code | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|
| 0317 | Premoulded joint filler board 12 mm thick (Rate inclusive of carriage) = 300x0.15 = 45 sqmPremoulded joint filler 12 mm thickMaterial | sqm | 45 | 380.00 | 17,100.00 |
| 0112 | Carpenter 2nd classLabour | day | 1 | 816.00 | 816.00 |
| 0114 | BeldarLabour | day | 3 | 736.00 | 2,208.00 |
| 9999 | SundriesMaterial | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 20,185.09
- Add 1 % Water charges on “W”
- 201.85
- TOTAL
- 20,386.94
- Add GST on “X” (multiplying factor 0.2127)
- 4,336.30
- TOTAL
- 24,723.24
- Add 15% CPOH on “Y”
- 3,708.49
- TOTAL
- 28,431.73
- Add Cess @ 1% on “Z”
- 284.32
- Cost for 300m length, 12mm width and 15cm depth
- 28,716.05
- Cost for one cm. depth one cm. width per metre length.
- 5.32
- Say
- 5.30
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1210. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.
Use this rate in a live estimate
This is the CPWD base analysis. A real estimate adjusts it for the project's inputs and the current cost index, then maps it to the tender's BOQ. Arched reads the tender, maps it to the applicable schedule, and flags where the numbers are exposed before submission.
See how estimation works