Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)

Item number
16.45
Analysis basis
12 mm
Priced inputs
4
Derived rate
₹5.30/ MM
D-01/RATE ANALYSISITEM 16.45

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.45 (Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)) is derived from 4 priced inputs for 12 mm and works out to ₹5.30 per mm after water charges, GST, CPOH and cess. The full build-up is below.

NOTES
  • and 300m in length
  • Labour for cutting the board in strips,
  • making the joints clean and dust free and
  • fixing etc. :
ANALYSIS OF RATES · ITEM 16.45DETAILS OF COST FOR 12 MM THICK 15CM DEEP
CodeTypeInputUnitQuantityRate (INR)Amount (INR)
0317MATPremoulded joint filler board 12 mm thick (Rate inclusive of carriage) = 300x0.15 = 45 sqmPremoulded joint filler 12 mm thicksqm45380.0017,100.00
0112LABCarpenter 2nd classday1816.00816.00
0114LABBeldarday3736.002,208.00
9999MATSundriesL.S.26.912.2761.09
BUILD-UP TO RATE
TOTAL
20,185.09
Add 1 % Water charges on “W”
+201.85
TOTAL
20,386.94
Add GST on “X” (multiplying factor 0.2127)
+4,336.30
TOTAL
24,723.24
Add 15% CPOH on “Y”
+3,708.49
TOTAL
28,431.73
Add Cess @ 1% on “Z”
+284.32
Cost for 300m length, 12mm width and 15cm depth
28,716.05
Cost for one cm. depth one cm. width per metre length.
5.32
SAY
₹5.30
D-02/SOURCEPRINTED PAGE 1210
PUBLISHED BY
Central Public Works Department (CPWD)
EDITION
DAR 2023 · Delhi
EFFECTIVE
2023-09-14Both volumes are dated 14 September 2023 on their title pages.
RETRIEVED
2026-09-08
GST
18%, added in each item's build-up
PRINTED PAGE
1210

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1210. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.