Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)
- Item number
- 16.45
- Analysis basis
- 12 mm
- Priced inputs
- 4
- Derived rate
- ₹5.30/ MM
Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.45 (Providing and fixing pre-moulded joint filler in expansion joints of RCC roads / CC pavements after making the joints dust free with high pressure air jet cleaners, all complete as per direction of the Engineer-in-Charge. (Pre-moulded joint fillers shall be made of bitumen hot sealing compound impregnated fibre board having impregnation more than 35%, conforming to IS:1838 for fibre board and IS: 1834 for hot sealing bitumen compound grade A.)) is derived from 4 priced inputs for 12 mm and works out to ₹5.30 per mm after water charges, GST, CPOH and cess. The full build-up is below.
- and 300m in length
- Labour for cutting the board in strips,
- making the joints clean and dust free and
- fixing etc. :
| Code | Type | Input | Unit | Quantity | Rate (INR) | Amount (INR) |
|---|---|---|---|---|---|---|
| 0317 | MAT | Premoulded joint filler board 12 mm thick (Rate inclusive of carriage) = 300x0.15 = 45 sqmPremoulded joint filler 12 mm thick | sqm | 45 | 380.00 | 17,100.00 |
| 0112 | LAB | Carpenter 2nd class | day | 1 | 816.00 | 816.00 |
| 0114 | LAB | Beldar | day | 3 | 736.00 | 2,208.00 |
| 9999 | MAT | Sundries | L.S. | 26.91 | 2.27 | 61.09 |
- TOTAL
- 20,185.09
- Add 1 % Water charges on “W”
- +201.85
- TOTAL
- 20,386.94
- Add GST on “X” (multiplying factor 0.2127)
- +4,336.30
- TOTAL
- 24,723.24
- Add 15% CPOH on “Y”
- +3,708.49
- TOTAL
- 28,431.73
- Add Cess @ 1% on “Z”
- +284.32
- Cost for 300m length, 12mm width and 15cm depth
- 28,716.05
- Cost for one cm. depth one cm. width per metre length.
- 5.32
- SAY
- ₹5.30
- PUBLISHED BY
- Central Public Works Department (CPWD)
- EDITION
- DAR 2023 · Delhi
- EFFECTIVE
- 2023-09-14Both volumes are dated 14 September 2023 on their title pages.
- RETRIEVED
- 2026-09-08
- GST
- 18%, added in each item's build-up
- PRINTED PAGE
- 1210
From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1210. For reference only. CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.