Providing and laying seal coat over prepared surface of road with bitumen heated in bitumen boiler fitted with the spray set spraying using 98 kg of bitumen of grade VG - 10 and blinding surface with 0.90 cum of stone aggregate of 6.7 mm size (Passing 11.2 mm sieve and retained on 2.36 mm sieve) per 100 sqm of road surface, including rolling and finishing with power road roller all complete

Item number
16.41
Analysis basis
Details of cost for 100sqm.
Priced inputs
20
Derived rate
130.85

Under the CPWD Delhi Analysis of Rates 2023 (Civil), item 16.41 Providing and laying seal coat over prepared surface of road with bitumen heated in bitumen boiler fitted with the spray set spraying using 98 kg of bitumen of grade VG - 10 and blinding surface with 0.90 cum of stone aggregate of 6.7 mm size (Passing 11.2 mm sieve and retained on 2.36 mm sieve) per 100 sqm of road surface, including rolling and finishing with power road roller all complete — is derived from 20 priced inputs and works out to ₹130.85 after water charges, GST, CPOH and cess. The full build-up is below.

  • Steam coal for heating bitumen @ 2 qunitals
  • per tonne of bitumen =2x0.098=1.96 qtl
  • Labour for cleaning road surface, heating
  • bitumen mixing and spreading aggregate :
  • (a) For heating and spraying bitumen :
  • (b) For cleaning :
  • (c) For screening and spraying aggregate :
  • (d) Misc :
  • (e) Misc :
  • (with thick wire)
CodeInputUnitQuantityRate (INR)Amount (INR)
2916Paving Asphalt VG -10 of approved qualityPaving Asphalt VG 10 of approved qualityMaterialtonne0.09833,530.003,285.94
0298Stone Aggregate (Single size) : 06 mm nominal sizeMaterialcum0.91,425.001,282.50
0370Coal (steam)Materialquintal1.96500.00980.00
0130MistryLabourday0.04897.0035.88
0138Sprayer (for bitumen, tar etc.)Labourday0.06816.0048.96
0114BeldarLabourday0.69736.00507.84
0128MateLabourday0.11816.0089.76
0114BeldarLabourday1.4736.001,030.40
0115CoolieLabourday1.4736.001,030.40
0128MateLabourday0.05816.0040.80
0114BeldarLabourday0.51736.00375.36
0113ChowkidarLabourday0.15736.00110.40
0101BhistiLabourday0.06816.0048.96
0003Hire charges of Diesel Road Roller - 8 to 10 tonneMachineryday0.063,350.00201.00
0007Hire charges of Coaltar SprayerMachineryday0.06400.0024.00
0001Hire charges of Coaltar Boiler 900 to 1400 litresMachineryday0.06900.0054.00
0364Wire brushMaterialeach0.0525.001.25
0365Soft brushMaterialeach0.1225.003.00
9999SundriesMaterialL.S.18.22.2741.31
9999Brooms and gunny bagsMaterialL.S.2.732.276.20
TOTAL
9,197.96
Add 1 % Water charges on “W”
91.98
TOTAL
9,289.94
Add GST on “X” (multiplying factor 0.2127)
1,975.97
TOTAL
11,265.91
Add 15% CPOH on “Y”
1,689.89
TOTAL
12,955.80
Add Cess @ 1% on “Z”
129.56
Cost for 100 sqm.
13,085.36
Cost per sqm.
130.85
Say
130.85

From the CPWD Delhi Analysis of Rates 2023 (Civil), Volumes I & II, printed page 1205. Reference only — CPWD amends rates through correction slips between editions, so verify against the official source before pricing a bid.